Bangalore/Project record

K-RERA · the public record

SATTVA AARANYA

Bengaluru South · Sattva Resi

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

14%construction reportedQ1 2026 filing
340units not bookedof 418 · Q1 2026 filing
23 Jan 2031declared completionK-RERA registration · read 20 Sep 2026

The record · free to read

Registration read 20 Sep 2026

Progress & dates

The timeline on file.

Promoter-reported construction

K-RERA quarterly filings · Q3 2025 to Q1 2026

declared completion

23 Jan 2031

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

K-RERA registration · read 20 Sep 2026

Inventory & scale

What this registration contains.

RC -3BHK
2
B2 -3BHK with staff room_West
83
A1-3BHK_West
77
B1 -3BHK with staff room_East
83
A2-3BHK_East
77
C -4BHK with staff room
61
C_t -4BHK with staff room and terrace
21
RA1 -2BHK_West
4
A2_T -3BHK_East with terrace
3
A1_T -3BHK_West with terrace
3
RA2 -2BHK_East
4

Filed categories, unchanged · K-RERA registration · read 20 Sep 2026

The whole registration

6.5registered acres

64.1registered units per acre

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual home.

From another project · Prestige Park Grove

A larger advertised area. Almost the same carpet area.

In Tower 14, E4 has 141 sq ft more saleable area than E2. Its carpet area is only 0.46 sq m larger. The report puts the two layouts side by side.

This illustrates the report format. These findings concern the named sample, not this project.

Read the sample report ↗
Prestige Park Grove · Tower 14 comparison · approved sample report
Prestige Park Grove · Tower 14 comparison · approved sample report

The source record

The details behind the headline.

K-RERA · PRM/KA/RERA/1251/310/PR/241225/008358

This project, on the record

The comparable facts of this project, from its own RERA registration record. Each context percentile names its exact comparison set, drawn from Quietlist’s full register store. The paid report adds drawing-read rows to this same table — what the filed plans show about the site, its edges and the unit layouts.

On the register

Declared completion23 January 2031
Land area26,406 sq m (6.5 acres)
Homes registered418
Tower/wing entries3
Unit mix2 × RC -3BHK, 83 × B2 -3BHK with staff room_West, 77 × A1-3BHK_West, 83 × B1 -3BHK with staff room_East, 77 × A2-3BHK_East, 61 × C -4BHK with staff room, 21 × C

In context

Density64.1 homes per acre
Density in context31st percentile of 787 Bengaluru South projects (median 77.3)

Values as crawled from the official K-RERA record; context percentiles name their comparison population.

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Registered units418Total inventory registered with K-RERA.
Official carpet area58,755 sqmRegulator-disclosed project-level carpet area, not vision-derived room sums.
Official built-up area132,130 sqmUseful scale context when comparing density and project cost.
Registered land area26,406 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI3.24Higher FAR generally means a denser vertical build, subject to site layout and open-space design.
Registered tower/wing entries3Official tower/wing count in the K-RERA detail page.
Parking total (reconciled)418Separate filed counts; these categories may overlap and are not added together.
Covered-parking field1,325Separate filed counts; these categories may overlap and are not added together.
Open-parking field60Separate filed counts; these categories may overlap and are not added together.
Garage field0Separate filed counts; these categories may overlap and are not added together.
Approved plan numberBBMP/Addl.Dir/JDSOUTH/0028/25-26Use this to match the sanctioned drawing set shown by the builder.
Plan approval date18-10-2025
Project start date01-01-2026

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
RC -3BHK20%238 sqm
B2 -3BHK with staff room_West8320%11,879 sqm
A1-3BHK_West7718%9,473 sqm
B1 -3BHK with staff room_East8320%12,026 sqm
A2-3BHK_East7718%9,473 sqm
C -4BHK with staff room6115%10,564 sqm
C_t -4BHK with staff room and terrace215%3,636 sqm
RA1 -2BHK_West41%363 sqm
A2_T -3BHK_East with terrace31%369 sqm
A1_T -3BHK_West with terrace31%369 sqm
RA2 -2BHK_East41%365 sqm

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
Tower A31138138110.3 m
Tower B31140140110.3 m
Tower C31140140110.3 m

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 418 official flat/unit rows, matching the 418 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
3 BHK326123.0-144.9 sqm44.3-52.9 sqm326
4 BHK84118.8-173.2 sqm43.0-61.6 sqm84
2 BHK890.7-91.3 sqm33.2-33.2 sqm8

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
Tower B14090.7-173.2 sqm33.2-61.6 sqm140
Tower C14090.7-173.2 sqm33.2-61.6 sqm140
Tower A138118.8-173.2 sqm43.0-61.6 sqm138
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
A 0301Tower A34 BHK173.2 sqm61.6 sqm1
A 0302Tower A33 BHK144.9 sqm52.9 sqm1
A 0303Tower A33 BHK123.0 sqm44.3 sqm1
A 0304Tower A33 BHK123.0 sqm44.3 sqm1
A 0305Tower A33 BHK143.1 sqm52.7 sqm1
A 0401Tower A44 BHK173.2 sqm61.6 sqm1

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

⚠ 1 litigation case on record

  • IA No.262/2024 & IA No.714/2024 — Debt Recovery Appellate Tribunal Chennai (2023)

6 of 33 compliance document slots are filed as Not Applicable; the remaining 27 slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)✓ On file (ESCOM/Electricity)
Water & sewage (BWSSB/KWSSB)✓ On file (KWSSB/Water)
Fire NOC✓ On file (Fire Force Department)
Pollution control (KSPCB)✓ On file (KSPCB)
Environmental clearance✓ On file (SEIAA)
Airport Authority height clearance✓ On file (Airport Authority of India)

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

Statutory approval status

RERA filing

7 of 8 applicable approvals are on file; still outstanding: KSPCB- PCB (10 Acres to 125 Acres). Pollution-control clearance (KSPCB) is among them — a high-importance clearance, so confirm it has been granted (not just applied for) before you book.

2 further authority slots are marked not applicable by the regulator.

Authority / NOCStatusDateFile
Water supply and sewage boardApproved12-09-2025BWSSB.pdf
KSPCB- PCB (10 Acres to 125 Acres)Applied03-10-2025View NOC
KSPCB- MOEF (Above 50 Acres)Approved27-02-2025Aaranya SEIAA.pdf
KPTCL- BESCOMApproved31-08-2024BESCOM.pdf
Fire and SafetyApproved05-05-2025Aaranya Fire NOC.pdf
Labour and Education DepartmentApproved21-08-2025Labour cess.pdf
Airport Authority of IndiaApproved09-12-2024AAI NOC AARANYA (1).pdf
BSNL/Telecommunication DepartmentApproved15-10-2024BSNL.pdf

Project team & certifications

RERA filing

K-RERA names 4 project professional/vendor rows across Chartered accountant, Engineer, Architect, Contractor. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
Chartered accountantAvneep L Mehta2254412014Bengaluru Urban, Karnataka - 560025
EngineerYOGESH H PBCC–BL/3.6-STRL.E.67:09-102010Bengaluru Urban, Karnataka - 560078
ArchitectRamamurthy GopalakrishnanCA 94/172921972Bengaluru Urban, Karnataka - 560008
ContractorConsolidated Construction Consortium Limited-1997Bengaluru Urban, Karnataka - 560078

Builder track record

RERA filing

Sattva has 23 other K-RERA-registered projects in our records — grouped across the several project-specific entities this developer registers under (e.g. this project is filed as “Sattva Resi”) (average reported construction progress 41%). 10 are past their declared completion deadline with no completion certificate recorded — but because K-RERA publishes OCs inconsistently, a project that has actually been finished and handed over still shows up this way, so this overstates real delays, especially for a high-volume established builder. That is a lower delayed rate than the K-RERA average across Bengaluru on the same measure.

Read this as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate — pull up a few of the builder’s other K-RERA registrations and check whether they’ve actually been delivered.

Financials & Construction Progress

Financial disclosures

RERA filing

Latest quarterly filing (2026-Q1): ₹10.13 Cr collected from buyers, ₹7.40 Cr withdrawn from the project's escrow account.

Construction progress8% → 14% (+6 pts)
Units sold/booked as registered78/418 (19%)
Buyer collections in available QPRs₹29.90 Cr
Escrow withdrawals in available QPRs₹20.79 Cr (0.70x collections)
  • Construction progress moved from 8% to 14% across the filed QPR window.
  • The builder has drawn 0.70x of buyer collections from escrow (about 70% of the ₹30 Cr collected) — money is largely staying in the regulated escrow account rather than being pulled out ahead of spend, which is the safer direction. A ratio near or above 1.0 would be the one to scrutinise.

QPR figures are developer-filed quarterly disclosures. Collections and withdrawals are not a project valuation; they are a sanity check for whether sales, construction progress, and escrow draws appear directionally aligned.

Declared construction cost ÷ registered units averages to ₹106.3 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.

RERA 70% project account is on file: YES BANK Kasturba Road IFSC Code : YESB0000022 Pin Code : 560001. RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Location & Connectivity

The nearest major job hub is ~17 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
MG Road / city centre11 km
Outer Ring Road / Manyata17 km
Electronic City19 km
Bellandur–Marathahalli belt19 km
Whitefield IT hub26 km
Kempegowda Int'l Airport36 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Sattva Resi. View Sattva Resi's full track record →
Sattva Resi has 11 projects registered in Bangalore, 1 completed.

Other projects by this builder in Bangalore

Sattva Simplicity
Filing overdue · 100% built · 74% sold
Park Cubix Phase 2
On track · 40% built · 60% sold
Sattva Songbird PH 2
On track · 3% built · 17% sold
Sattva Springs
On track · 36% built · 39% sold
Sattva Forest Ridge
On track · 15% built · 63% sold

Other RERA-registered projects in Nayanda Halli

Major developers building in Nayanda Halli

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.

Own a unit in Sattva Aaranya?

Sell directly to Quietlist's pre-screened buyer list — flat fee, no broker commission.

List your unit →

Last checked against the RERA register: 20 Sep 2026