Bangalore/Project record

K-RERA · the public record

VASATHI AVANTE

Bengaluru North · Vasathi Housing

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Dec 2018declared completionK-RERA registration · read 20 Sep 2026
380registered unitsK-RERA registration · read 20 Sep 2026

The record · free to read

Registration read 20 Sep 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2018

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

K-RERA registration · read 20 Sep 2026

Inventory & scale

What this registration contains.

2BHK 2T
110

Filed categories, unchanged · K-RERA registration · read 20 Sep 2026

The whole registration

5.3registered acres

71.5registered units per acre

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual home.

From another project · Prestige Park Grove

A larger advertised area. Almost the same carpet area.

In Tower 14, E4 has 141 sq ft more saleable area than E2. Its carpet area is only 0.46 sq m larger. The report puts the two layouts side by side.

This illustrates the report format. These findings concern the named sample, not this project.

Read the sample report ↗
Prestige Park Grove · Tower 14 comparison · approved sample report
Prestige Park Grove · Tower 14 comparison · approved sample report

The source record

The details behind the headline.

K-RERA · PRM/KA/RERA/1251/309/PR/171208/001088

This project, on the record

The comparable facts of this project, from its own RERA registration record. Each context percentile names its exact comparison set, drawn from Quietlist’s full register store. The paid report adds drawing-read rows to this same table — what the filed plans show about the site, its edges and the unit layouts.

On the register

Declared completion31 December 2018
Land area21,499 sq m (5.3 acres)
Homes registered380
Tower/wing entries3
Unit mix110 × 2BHK 2T

In context

Density71.5 homes per acre
Density in context45th percentile of 525 Bengaluru North projects (median 75.4)

Values as crawled from the official K-RERA record; context percentiles name their comparison population.

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Registered units380Total inventory registered with K-RERA.
Official carpet area7,218 sqmRegulator-disclosed project-level carpet area, not vision-derived room sums.
Registered land area21,499 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI2.24Higher FAR generally means a denser vertical build, subject to site layout and open-space design.
Registered tower/wing entries3Official tower/wing count in the K-RERA detail page.
Parking total (reconciled)419Separate filed counts; these categories may overlap and are not added together.
Open-parking field44Separate filed counts; these categories may overlap and are not added together.
Garage field0Separate filed counts; these categories may overlap and are not added together.
Project start date01-01-2014

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
2BHK 2T110100%7,218 sqm

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
A(ASPEN)11116117-
B(BIRCH)11152190-
C(CEDAR)14112112-

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

No litigation declared on this project's K-RERA filing.

All 15 standard compliance document slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

⚠ Registration validity has lapsed: originally due 31 Dec 2018, extended (Section 6 Extension) to 30 Sep 2019 — both dates have passed with no OC on file. The extension on file was granted on 13 Jun 2022 (K-RERA extension no. EX/PRM/KA/RERA/1251/309/PR/220613/001088) — it has been used, its deadline has also passed, and no further extension is recorded.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)✓ On file (All NOCs from Authority)
Water & sewage (BWSSB/KWSSB)✓ On file (All NOCs from Authority)
Fire NOC✓ On file (All NOCs from Authority)
Pollution control (KSPCB)✓ On file (All NOCs from Authority)
Environmental clearance✓ On file (All NOCs from Authority)
Airport Authority height clearance✓ On file (All NOCs from Authority)

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

K-RERA enforcement record (the regulator's own defaulter list & penalty orders)

⚠ Listed on K-RERA's official DEFAULTER list.

K-RERA complaint orders (19 complaints against a project of this name on K-RERA's orders register)

PartiesRelief soughtDisposalOrder date
MS SANTHI ADIGOPULA vs M/S.VASATHI HOUSING LTDThe respondent to secure refund of money with interest + compensation till now.AUTHORITY25/09/2023
Basavaraj Badasad vs VASATHI AVANTETo initiate action under RERA section 7 & 8AUTHORITY25/04/2024
VIKAS SHARMA vs VASATHI HOUSING LTD.Attachment before Judgment of two unsold 2BHK flats of the respondent to secure refund of money with interest + compensation Rs.2,50,00,000/-AUTHORITY22/09/2023
RAGAVENDRA DIXIT vs VASATHI AVANTEDirect the Respondent to register the Sale Deed in favour of Complainant and deliver the possession of the flat No. W1-B- 1102 forthwith.AUTHORITY20/12/2023
TRISHALA BASTI vs VASATHI HOUSEING LTD.Hence it is humbly prayed before the Authority that: 1. Respondent be directed to complete the flat and all amenities and register the property without Occupancy certificate by June 30, 2020. 2. RespAUTHORITY15/12/2023
Harish S Dattatreya vs Vasathi Housing LtdEnforce builder to complete project or handover to 3rd party. Restrain from alienating all unsold inventory.Return deposits/funds legally belonging to association.Compensate for delay/deviationAUTHORITY15/05/2021
Badri Krishnan vs P V Ravindra KumarCompensation and enforce registrationAUTHORITY11/02/2023
TEENA K JAIN vs VASATHI HOUSING LTDkindly direct the Respondent to register Sale Deed and also award the Complainant with Rs.1,00,000/- Compensation for the delay in registering the Sale Deed. and pass any other orderAUTHORITY11/02/2023
AMARESH MAREKAR vs VASANTHI HOUSING LTD.Pass on order to Builder to Provide indoor Badminton court as per the agreementAUTHORITY09/10/2023
HARISH S DATTATREYA vs VASATHI AVANTHEDelay Compensation & project completion as earlierAUTHORITY07/03/2024
HARISH S DATTATREYA vs VASATHI AVANTHEDelay Compensation & project completion as earlierAUTHORITY07/03/2024
sarvesh s vs vasathi avanthedelay charges and early completion of project. Detailed statement attached as DOC-1AUTHORITY06/09/2023
Amaresh Marekar vs Vasathi Housing LtdCorpus and Maintenance transfer to association with panelty. Transfer of amenities title to association. Penalty for Delay . Restrain on landowners from alienating any apartment in Vasathi Avante.AUTHORITY05/06/2026
ARUNAVA GHOSH vs VASNTHI HOUSING LTD.To remedy the situation and enforce the builder to complete the project. Provide monetary relief in terms of delay penalty, damages and mental harassment caused due to huge delay and non-cooperation.AUTHORITY03/11/2023
Shivaraj N Arali vs Vasathi Housing LtdIt is this honorable core to pass orders restraining the builder from selling away these flats by passing an order of attachment before judgement in the interest of equity and justiceAUTHORITY03/06/2026
S Chandrashekar vs Vasathi Housing LtdIt is this hon'able court to pass orders restraining the builder from selling away these unsold flats by passing and order of attachment before judgement in the interest of equity and justice.AUTHORITY03/06/2026
Shiddalingayya Veerapurmath vs Vasathi Housing LtdThis Hon'ble court to pass orders restraining the builder by selling away these unsold flats by passing and order of attachment before judgement in the interest of equity and justiceAUTHORITY03/06/2026
SANDEEP KARMAKAR vs Vasathi Housing LtdA) Replacement of the toilet commode. B) Filling Cracks and Painting C) No coercive or threatening actions such as cancellation of booking are taken against me.AUTHORITY03/06/2026
SUNIL BHADRAN vs Vasathi Housing LtdKindly allow Builder to proceed with the registration against my flat W3-B-1004AUTHORITY03/04/2025

⚠ Matched by PROJECT NAME (the orders register carries no registration number) — confirm the respondent above is this project's builder before relying on it.

Complaints on this project's K-RERA page (26 complaints listed against this promoter)

ComplaintSubject (as filed)ProjectStatus
CMP/190802/0003801
02-08-2019
hand over of the project not done after completion of due timeVASATHI AVANTEDISPOSED AO
CMP/190906/0003414
06-09-2019
PATHETIC QUALITY OF WORK, VERY LONG DELAY WITH NO SIGNS OF COMPLETION OF APARTMENT BUILDING AND RELATED AMENITIESVASATHI AVANTEDISPOSED AO
CMP/190917/0004214
17-09-2019
PATHETIC QUALITY OF WORK, VERY LONG DELAY WITH NO SIGNS OF COMPLETION OF APARTMENT BUILDING AND RELATED AMENITIESVASATHI AVANTEDISPOSED AO
CMP/191016/0004444
16-10-2019
Delay in completion and possessionVASATHI AVANTEDISPOSED AO
CMP/191114/0004720
14-11-2019
Cancellation of fraudulent Agreement for sale induced by the respondent and refund of Rs.75,95,821/- with 24% of interest PAVASATHI AVANTEDISPOSED AUTHORITY FULLBENCH
CMP/191226/0005069
26-12-2019
Time bound Project Completion and other reliefVASATHI AVANTEDISPOSED AUTHORITY
CMP/200203/0005355
03-02-2020
Representation regarding incomplete project, expired project completion date, inhabitable living conditions amounting to life threat and license cancellation of Vasathi Housing Pvt. LtdVASATHI AVANTEDISPOSED AUTHORITY FULLBENCH
CMP/200211/0005392
11-02-2020
Seeking justice and initiating criminal charges against the promoterVASATHI AVANTEDISPOSED AO

Listed on the project's own K-RERA detail page (registration-exact source). Rows on the promoter's other projects are track-record context — read the subject text, it is the complainant's own filed wording.

Project team & certifications

RERA filing

K-RERA names 2 project professional/vendor rows across Architect, Structural engineer. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
ArchitectABHAY IRITTY ZACHARIAH-1975Bengaluru, Karnataka.
Structural engineerB.E.Pruthviraja---

Financials & Construction Progress

Financial disclosures

RERA filing

⚠ No quarterly financial disclosures (collections, escrow withdrawals) on record, despite no completion certificate yet — meaning we can't verify the project's cashflows against its construction progress. Worth asking the builder directly why no quarterly filings are available.

Declared construction cost ÷ registered units averages to ₹28.0 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.

RERA 70% project account is on file: STATE BANK OF INDIA Hebbal (IFSC SBIN0001316, a/c …1869). RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Construction photo filings

RERA filing

K-RERA has 1 project-photo upload.

These are developer-uploaded progress photos in the official document catalog. We do not treat them as proof of current site condition; use them as a prompt to ask for newer dated photos or a site visit. Individual filings are listed in the document catalog below.

Location & Connectivity

The nearest major job hub is ~2 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Outer Ring Road / Manyata2 km
MG Road / city centre10 km
Bellandur–Marathahalli belt16 km
Whitefield IT hub17 km
Kempegowda Int'l Airport18 km
Electronic City24 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Vasathi Housing.

Other RERA-registered projects in Kothanur

Major developers building in Kothanur

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.