Gurgaon/Project record

HRERA · the public record

Ishan Singh

SECTOR-78, VILLAGE- NAURANGPU R · Spaze Towers

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

486units in latest filingQ4 2023 filing
0units sold that quarterQ4 2023 filing
31 Dec 2025registration expiryHRERA registration · read 20 Sep 2026

The record · free to read

Registration read 20 Sep 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

registration expiry

31 Dec 2025

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

HRERA registration · read 20 Sep 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

HRERA ·

Escrow account

What has moved through the RERA escrow account?

Across 18 filed quarterly reports, Ishan Singh records ₹65 L paid into and ₹67 L withdrawn from its RERA escrow account, with a latest recorded balance of ₹0 L.

₹65 L

into the escrow account

₹67 L

withdrawn

₹0 L

latest balance

Amounts as filed in the developer's own quarterly progress reports to HRERA, summed across the quarters on record.

Source · HRERA quarterly progress reports

Sales Traction, Quarter by Quarter

Units the developer reported booking in each quarterly HRERA filing — the closest public read on real demand.

QuarterUnits bookedTotal units
2019 Q31486
2019 Q41486
2020 Q10486
2020 Q20486
2020 Q30486
2020 Q40486
2021 Q10486
2021 Q20486
2021 Q30486
2021 Q40486
2022 Q10486
2022 Q20486
2022 Q30486
2022 Q40486
2023 Q10486
2023 Q20486
2023 Q30486
2023 Q40486

Escrow Account Activity

Money moving through the RERA-mandated escrow account each quarter. Withdrawals from it are statutorily meant to fund construction milestones.

QuarterDepositedWithdrawnBalance
2019 Q3₹22 L₹22 L₹2 L
2019 Q4₹22 L₹22 L₹2 L
2020 Q1₹2 L₹3 L₹2 L
2020 Q2₹1 L₹2 L₹1 L
2020 Q3₹5 L₹5 L₹1 L
2020 Q4₹1 L₹1 L₹1 L
2021 Q1₹3 L₹3 L₹1 L
2021 Q2₹2 L₹2 L₹1 L
2021 Q3₹2 L₹2 L₹0 L
2021 Q4₹1 L₹1 L₹0 L
2022 Q1₹2 L₹2 L₹0 L
2022 Q2₹1 L₹1 L₹0 L
2022 Q3₹0 L₹0 L₹0 L
2022 Q4₹0 L₹0 L₹0 L
2023 Q1₹0 L₹0 L₹0 L
2023 Q2₹0 L₹0 L₹0 L
2023 Q3₹0 L₹0 L₹0 L
2023 Q4₹0 L₹0 L₹0 L

Builder Record

Spaze has 5 other Gurgaon projects on the HRERA register; 0 are past the declared completion date with no OC yet, 5 delivered. Read it as a spot-check list for a pattern, not a delay rate.

  • Auto Max A Unit of Omaxe Auto LTD — declared 2021-09-10 · OC on record
  • Auto Max A Unit of Omaxe Auto LTD — declared 2020-06-30 · OC on record
  • Mohinder Kaur & Others — declared 2020-12-30 · OC on record
  • Spaze Corporate Park — declared 2020-06-30 · OC on record

Location & Connectivity

The nearest major job hub is ~3 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
IMT Manesar3 km
Golf Course Road belt17 km
Cyber City / DLF Cyber Hub20 km
Udyog Vihar20 km
IGI Airport, Delhi26 km
Connaught Place, Delhi39 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Spaze. View Spaze's full track record →
Spaze has 6 projects registered in Gurgaon, 5 completed, 1 past RERA deadline.

Other projects by this builder in Gurgaon

Auto MAX A Unit OF Omaxe Auto Ltd,
Completed · 96% sold
Auto MAX A Unit OF Omaxe Auto Ltd,
Completed · 98% sold
Mohinder Kaur & Others
Completed · 95% sold
Spaze Corporate Park
Completed · 95% sold

Other RERA-registered projects in Sector 79

Major developers building in Sector 79

Figures are the developer's own quarterly disclosures on the Haryana RERA register. "Sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Gurgaon project-health tool.

Own a unit in Ishan Singh?

Sell directly to Quietlist's pre-screened buyer list — flat fee, no broker commission.

List your unit →

Last checked against the RERA register: 20 Sep 2026