HRERA · the public record
Spaze Corporate Park
SECTOR 69-70, VILLAGE BADSHAH PUR, GURUGRAM · Spaze Towers
Know the project.
Then choose your home.
The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.
The record · free to read
Registration read 20 Sep 2026Progress & dates
The timeline on file.
Available record
No construction trend to plot.
The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.
registration expiry
30 Jun 2020
The registered date and a construction update answer different questions. Neither is a confirmation of possession.
HRERA registration · read 20 Sep 2026
From another project
See the report before you buy.
A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.
Read a sample report ↗The source record
The details behind the headline.
HRERA ·
Escrow account
What has moved through the RERA escrow account?
Across 6 filed quarterly reports, Spaze Corporate Park records ₹30.32 Cr paid into and ₹30.43 Cr withdrawn from its RERA escrow account, with a latest recorded balance of ₹1 L.
₹30.32 Cr
into the escrow account
₹30.43 Cr
withdrawn
₹1 L
latest balance
Amounts as filed in the developer's own quarterly progress reports to HRERA, summed across the quarters on record.
Source · HRERA quarterly progress reports
Sales Traction, Quarter by Quarter
Units the developer reported booking in each quarterly HRERA filing — the closest public read on real demand.
| Quarter | Units booked | Total units |
|---|---|---|
| 2020 Q1 | 2 | 561 |
| 2020 Q2 | 0 | 561 |
| 2020 Q3 | 0 | 561 |
| 2020 Q4 | 0 | 561 |
| 2021 Q1 | 2 | 561 |
| 2021 Q2 | 0 | 561 |
Escrow Account Activity
Money moving through the RERA-mandated escrow account each quarter. Withdrawals from it are statutorily meant to fund construction milestones.
| Quarter | Deposited | Withdrawn | Balance |
|---|---|---|---|
| 2020 Q1 | ₹16.56 Cr | ₹16.66 Cr | ₹2 L |
| 2020 Q2 | ₹1.81 Cr | ₹1.77 Cr | ₹6 L |
| 2020 Q3 | ₹4.87 Cr | ₹4.92 Cr | ₹0 L |
| 2020 Q4 | ₹2.67 Cr | ₹2.67 Cr | ₹0 L |
| 2021 Q1 | ₹3.65 Cr | ₹3.60 Cr | ₹6 L |
| 2021 Q2 | ₹76 L | ₹81 L | ₹1 L |
Builder Record
Spaze has 5 other Gurgaon projects on the HRERA register; 1 is past the declared completion date with no OC yet, 4 delivered. Read it as a spot-check list for a pattern, not a delay rate.
- Auto Max A Unit of Omaxe Auto LTD — declared 2021-09-10 · OC on record
- Auto Max A Unit of Omaxe Auto LTD — declared 2020-06-30 · OC on record
- Ishan Singh — declared 2025-12-31
- Mohinder Kaur & Others — declared 2020-12-30 · OC on record
Location & Connectivity
The nearest major job hub is ~9 km away — a manageable everyday commute to a major job hub.
| Landmark | Straight-line |
|---|---|
| Golf Course Road belt | 9 km |
| IMT Manesar | 10 km |
| Cyber City / DLF Cyber Hub | 13 km |
| Udyog Vihar | 13 km |
| IGI Airport, Delhi | 19 km |
| Connaught Place, Delhi | 32 km |
Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.