Luminare Phase I

SECTOR 59, VILLAGE BEHRAMPUR, TEHSIL SOHNA, GURUGRAM · Mahindra Homes

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

120units in latest filingQ1 2026 filing
65units sold that quarterQ1 2026 filing
31 Mar 2020registration expiryHRERA registration · read 20 Sep 2026

The record · free to read

Registration read 20 Sep 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

registration expiry

31 Mar 2020

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

HRERA registration · read 20 Sep 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

HRERA ·

Escrow account

What has moved through the RERA escrow account?

Across 6 filed quarterly reports, Luminare Phase I records ₹4 L paid into and ₹0 L withdrawn from its RERA escrow account, with a latest recorded balance of ₹4 L.

₹4 L

into the escrow account

₹0 L

withdrawn

₹4 L

latest balance

Amounts as filed in the developer's own quarterly progress reports to HRERA, summed across the quarters on record.

Source · HRERA quarterly progress reports

Sales Traction, Quarter by Quarter

Units the developer reported booking in each quarterly HRERA filing — the closest public read on real demand.

QuarterUnits bookedTotal units
2024 Q40120
2025 Q10120
2025 Q20120
2025 Q30120
2025 Q40120
2026 Q165120

Escrow Account Activity

Money moving through the RERA-mandated escrow account each quarter. Withdrawals from it are statutorily meant to fund construction milestones.

QuarterDepositedWithdrawnBalance
2024 Q4₹0 L₹0 L₹0 L
2025 Q1₹0 L₹0 L₹0 L
2025 Q2₹0 L₹0 L₹0 L
2025 Q3₹0 L₹0 L₹0 L
2025 Q4₹0 L₹0 L₹0 L
2026 Q1₹4 L₹0 L₹4 L

Builder Record

Mahindra Lifespaces has 2 other Gurgaon projects on the HRERA register; 1 is past the declared completion date with no OC yet, 1 delivered. Read it as a spot-check list for a pattern, not a delay rate.

  • Luminare Phase 2 — declared 2021-03-31 · OC on record
  • Luminare Phase 3 — declared 2026-08-23

Location & Connectivity

The nearest major job hub is ~4 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Golf Course Road belt4 km
Cyber City / DLF Cyber Hub10 km
Udyog Vihar11 km
IGI Airport, Delhi17 km
IMT Manesar17 km
Connaught Place, Delhi27 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Mahindra Homes. View Mahindra Homes's full track record →
Mahindra Homes has 3 projects registered in Gurgaon, 2 completed, 1 past RERA deadline.

Other projects by this builder in Gurgaon

Luminare Phase 3
Past deadline · 70% sold
Luminare Phase 2
Completed · 43% sold

Other RERA-registered projects in Sector 66

Major developers building in Sector 66

Figures are the developer's own quarterly disclosures on the Haryana RERA register. "Sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Gurgaon project-health tool.