Tathastu I
SECTOR 5, VILLAGE SOHNA · Desi Construction
Know the project.
Then choose your home.
The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.
The record · free to read
Registration read 20 Sep 2026Progress & dates
The timeline on file.
Available record
No construction trend to plot.
The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.
registration expiry
14 Nov 2027
The registered date and a construction update answer different questions. Neither is a confirmation of possession.
HRERA registration · read 20 Sep 2026
From another project
See the report before you buy.
A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.
Read a sample report ↗The source record
The details behind the headline.
HRERA ·
Escrow account
What has moved through the RERA escrow account?
Across 12 filed quarterly reports, Tathastu I records ₹305.56 Cr paid into and ₹299.87 Cr withdrawn from its RERA escrow account, with a latest recorded balance of ₹5.69 Cr.
₹305.56 Cr
into the escrow account
₹299.87 Cr
withdrawn
₹5.69 Cr
latest balance
Amounts as filed in the developer's own quarterly progress reports to HRERA, summed across the quarters on record.
Source · HRERA quarterly progress reports
Sales Traction, Quarter by Quarter
Units the developer reported booking in each quarterly HRERA filing — the closest public read on real demand.
| Quarter | Units booked | Total units |
|---|---|---|
| 2023 Q2 | 1730 | 2165 |
| 2023 Q3 | 39 | 2165 |
| 2023 Q4 | 42 | 2165 |
| 2024 Q1 | 54 | 2165 |
| 2024 Q2 | 36 | 2165 |
| 2024 Q3 | 17 | 2165 |
| 2024 Q4 | 22 | 2165 |
| 2025 Q1 | 9 | 2165 |
| 2025 Q2 | 29 | 2165 |
| 2025 Q3 | 9 | 2165 |
| 2025 Q4 | 9 | 2165 |
| 2026 Q1 | 20 | 2165 |
Escrow Account Activity
Money moving through the RERA-mandated escrow account each quarter. Withdrawals from it are statutorily meant to fund construction milestones.
| Quarter | Deposited | Withdrawn | Balance |
|---|---|---|---|
| 2023 Q2 | ₹72.54 Cr | ₹72.08 Cr | ₹46 L |
| 2023 Q3 | ₹44.39 Cr | ₹43.85 Cr | ₹99 L |
| 2023 Q4 | ₹8.89 Cr | ₹6.50 Cr | ₹3.39 Cr |
| 2024 Q1 | ₹13.18 Cr | ₹9.17 Cr | ₹7.40 Cr |
| 2024 Q2 | ₹42.29 Cr | ₹49.60 Cr | ₹10 L |
| 2024 Q3 | ₹6.61 Cr | ₹6.69 Cr | ₹2 L |
| 2024 Q4 | ₹42.81 Cr | ₹42.62 Cr | ₹21 L |
| 2025 Q1 | ₹25.81 Cr | ₹24.84 Cr | ₹1.17 Cr |
| 2025 Q2 | ₹7.00 Cr | ₹7.82 Cr | ₹0 L |
| 2025 Q3 | ₹2.67 Cr | ₹2.11 Cr | ₹91 L |
| 2025 Q4 | ₹30.85 Cr | ₹30.80 Cr | ₹96 L |
| 2026 Q1 | ₹8.53 Cr | ₹3.80 Cr | ₹5.69 Cr |
Builder Record
Desi Construction has 1 other Gurgaon project on the HRERA register; 0 are past the declared completion date with no OC yet. Read it as a spot-check list for a pattern, not a delay rate.
- Tathastu II — declared 2027-11-14
Location & Connectivity
The nearest major job hub is ~23 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.
| Landmark | Straight-line |
|---|---|
| IMT Manesar | 23 km |
| Golf Course Road belt | 23 km |
| Cyber City / DLF Cyber Hub | 29 km |
| Udyog Vihar | 30 km |
| IGI Airport, Delhi | 35 km |
| Connaught Place, Delhi | 45 km |
Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.