Registration read 20 Sep 2026Progress & dates
The timeline on file.
Available record
No construction trend to plot.
The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.
registration expiry
29 Jun 2026
The registered date and a construction update answer different questions. Neither is a confirmation of possession.
HRERA registration · read 20 Sep 2026
From another project
See the report before you buy.
A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.
Read a sample report ↗The source record
The details behind the headline.
HRERA ·
Escrow account
What has moved through the RERA escrow account?
Across 6 filed quarterly reports, The Ark records ₹35.80 Cr paid into and ₹34.76 Cr withdrawn from its RERA escrow account, with a latest recorded balance of ₹1.05 Cr.
₹35.80 Cr
into the escrow account
₹34.76 Cr
withdrawn
₹1.05 Cr
latest balance
Amounts as filed in the developer's own quarterly progress reports to HRERA, summed across the quarters on record.
Source · HRERA quarterly progress reports
Sales Traction, Quarter by Quarter
Units the developer reported booking in each quarterly HRERA filing — the closest public read on real demand.
| Quarter | Units booked | Total units |
|---|---|---|
| 2024 Q3 | 0 | 77 |
| 2024 Q4 | 9 | 77 |
| 2025 Q1 | 0 | 77 |
| 2025 Q2 | 1 | 77 |
| 2025 Q3 | 1 | 77 |
| 2025 Q4 | 1 | 77 |
Escrow Account Activity
Money moving through the RERA-mandated escrow account each quarter. Withdrawals from it are statutorily meant to fund construction milestones.
| Quarter | Deposited | Withdrawn | Balance |
|---|---|---|---|
| 2024 Q3 | ₹5.23 Cr | ₹5.24 Cr | ₹0 L |
| 2024 Q4 | ₹9.51 Cr | ₹9.40 Cr | ₹11 L |
| 2025 Q1 | ₹4.08 Cr | ₹4.12 Cr | ₹7 L |
| 2025 Q2 | ₹3.67 Cr | ₹2.87 Cr | ₹88 L |
| 2025 Q3 | ₹9.81 Cr | ₹9.52 Cr | ₹1.16 Cr |
| 2025 Q4 | ₹3.50 Cr | ₹3.61 Cr | ₹1.05 Cr |
Builder Record
Hero Realty has 4 other Gurgaon projects on the HRERA register; 0 are past the declared completion date with no OC yet. Read it as a spot-check list for a pattern, not a delay rate.
- Hero Earth Commercial Shops — declared 2027-06-30
- The Palatial Phase 1 — declared 2030-06-30
- The Palatial Phase 2 — declared 2030-06-30
- The Palatial Phase 4 & Commercial — declared 2030-06-30
Location & Connectivity
The nearest major job hub is ~5 km away — a manageable everyday commute to a major job hub.
| Landmark | Straight-line |
|---|---|
| IMT Manesar | 5 km |
| Golf Course Road belt | 15 km |
| Cyber City / DLF Cyber Hub | 17 km |
| Udyog Vihar | 17 km |
| IGI Airport, Delhi | 22 km |
| Connaught Place, Delhi | 36 km |
Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.