MahaRERA Property Intelligence · Mumbai City

30 LITTLE GIBBS

P51900053421 · MALABAR · promoter Sila Malabar Hill

Certificate SignedDue 30 Jun 2029

Delivery & Registration

MahaRERA registrationP51900053421
Registered on31 Oct 2023
Promoter-declared completion30 Jun 2029
Current statusCertificate Signed
Against today35 months to the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+42.

BuildingWingsFloorsDeclared completion
30 LITTLE GIBBS1G+42-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Legal & Litigation

The promoter has declared 2 court cases on this project to MahaRERA. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your flat. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
High Court2104 of 20082008Disposssed Off
Supreme Court5137-5138 of 20082008Dispossed Off

Location, Land & Connectivity

Located at MALABAR, LITTLE GIBBS ROAD, Ward GSouth, Mumbai City, 400006. Per the filed land record, the plot is bounded to the north by PRIVATE PASSAGE OF CS NO 369 MALABAR ANDCUMBALL, to the south by LITTLE GIBBS ROAD, to the east by 1-369 MALABAR AND CUMBALLA HILL and to the west by 369 OFMALABAR AND CUMBALLA HILL DIVISION. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Malabar Hill

Lodha Malabar
possession by Jun 2027 · Lodha Developers Limited
Earth 280
possession by Aug 2027 · Earth Builders
Kalpataru Azuro
possession by Dec 2027 · Kalpataru Properties Limited
Ruparel House
possession by Dec 2027 · R House Realty Private Limited
Waterview
possession by Jun 2028 · Lodha Developers Limited
Sambhav
possession by Dec 2028 · Helictite Residency Private Limited

Major developers building in Malabar Hill

Other RERA-registered projects in Mumbai City

36 Babulnath
declared completion Sep 2021 · Vinod Mohanlal Jain
379 Vista
possession by Jan 2029 · Ajwaa Developers
41 Grandstand
possession by Jun 2029 · Ramesh Builders
42 East Park
declared completion Apr 2026 · Madhupuri Homes
47 Race Course
possession by Dec 2027 · Akshay Sthapatya Pvt. Ltd.
52 Avenue
declared completion Dec 2024 · Heks Realty

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026