Mumbai/Project record

MahaRERA · the public record

9ALMEIDA

Mumbai City · SACHISHAAN DEVELOPERS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Dec 2019declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2019

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51900006016

Delivery and registration

When is the project declared for completion?

9ALMEIDA is registered with MahaRERA as P51900006016 and the promoter has declared completion for 31 Dec 2019.

31 Dec 2019

declared completion

81months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51900006016
Registered on14 Aug 2017
Promoter-declared completion31 Dec 2019
Current statusCertificate Signed
Against todayabout 81 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for 9ALMEIDA record 10 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 10 quarterly progress reports on record since registration, with no current default.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for 9ALMEIDA in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+17.

BuildingWingsFloorsDeclared completion
9ALMEIDA1G+17-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered31 Dec 2019Due to certain events and circumstances, we could not complete the said project on the said date. The construction activity has been almost completed and due to certain approvals f

Location, Land & Connectivity

Located at Mumbai City, Mumbai City, 400050. Per the filed land record, the plot is bounded to the north by FOURTH ROAD, to the south by FINAL PLOT NO 91, to the east by PLOT NO 90 OF BANDRA MUNICIPAL HOSPITAL and to the west by PLOT NO 93. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~4 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Bandra Kurla Complex (BKC)4 km
Chhatrapati Shivaji Int'l Airport5 km
Lower Parel / Worli business district6 km
Andheri MIDC / SEEPZ9 km
Powai / Hiranandani business park11 km
Nariman Point / Fort14 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Bandra West

Bandra Boon CHS LTD
possession by Sep 2026 · Mass Jaks Associate Ventures
Aryan Tower
Not filing quarterly progress reports · possession by Dec 2026 · Suchit Developers
Brightland
possession by Dec 2026 · Sambhavparshva Developers Private Limite
Hill Casa
possession by Dec 2026 · Husain Taher Patni
Hill View
possession by Dec 2026 · L Nagpal Builders LLP
Manthan Embassy
possession by Dec 2026 · Manthan Development Corporation

Major developers building in Bandra West

Other RERA-registered projects in Mumbai City

9th Avenue
declared completion Mar 2025 · Aureum Homes LLP
A.m. Gazdar Residency
possession by Dec 2027 · Gazdar Properties
A. M. Residency
possession by Dec 2026 · Alfa Mana Realtors PVT LTD
A.R Vintage
declared completion Jun 2026 · A.R Associates
Aadi Arpan
declared completion Jul 2026 · Aadi Shikhar LLP
Aadi Arpan NX
possession by Dec 2027 · Aadi Shikhar LLP

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026