Mumbai/Project record

MahaRERA · the public record

A AND O FLORANTE

Sambhaji nagar · M/S CHARMEE ENTERPRISES

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Dec 2022declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2022

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800008290

Delivery and registration

When is the project declared for completion?

A AND O FLORANTE is registered with MahaRERA as P51800008290 and the promoter has declared completion for 30 Dec 2022.

30 Dec 2022

declared completion

45months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800008290
Registered on18 Aug 2017
Promoter-declared completion30 Dec 2022
Current statusCertificate Signed
Against todayabout 45 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for A AND O FLORANTE record 22 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 22 quarterly progress reports on record since registration, with no current default.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for A AND O FLORANTE in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+21.

BuildingWingsFloorsDeclared completion
A AND O FLORANTE1G+2131 Dec 2021

Legal and disputes

What disputes are disclosed?

1 complaint is on the MahaRERA record for A AND O FLORANTE, with orders passed in 1 of them.

1complaint

1with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
SM1250005005/04/2025Prabhash Tiwari vs M/S CHARMEE ENTERPRISESorder passed

Legal & Litigation

The promoter has declared 5 court cases on this project to MahaRERA. 5 are still pending. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your home. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
High CourtNM 29/2016 IN COMMERCIAL SUIT NO 54/20162016Pending
High CourtCWP/248/20152015Pending
High Court57222018Pending
City Civil Court3062018Pending
High Court40322018Pending

Location, Land & Connectivity

Located at Sambhaji nagar, sambhaji nagar, Kurla, Mumbai Suburban, 400069. Per the filed land record, the plot is bounded to the north by CTS 1PT -CTS 37, to the south by CTS 7pt-CTS 8, to the east by DP ROAD and to the west by WESTERN RAILWAY BOUNDARY. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~3 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Andheri MIDC / SEEPZ3 km
Chhatrapati Shivaji Int'l Airport3 km
Bandra Kurla Complex (BKC)6 km
Powai / Hiranandani business park6 km
Lower Parel / Worli business district13 km
Nariman Point / Fort21 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Andheri East

Anamika
possession by Sep 2026 · NEW India Constructions
Romell Myra
Deregistered by MahaRERA · possession by Sep 2026 · Romell Properties Private Limited
Romell Orbis
possession by Sep 2026 · Romell Properties Private Limited
Amey Apartments
possession by Oct 2026 · Amey Realty AND Construction LLP
Elegant Residency
possession by Dec 2026 · Elegant Builders AND Developers
Girnar Residency Wing B Phase 1
possession by Dec 2026 · Nidhaan Realty LLP

Major developers building in Andheri East

Other RERA-registered projects in Mumbai Suburban

A AND O Palazzio
declared completion Jul 2019 · Ashapura Options Private Limited
A H Atlantis
possession by Dec 2030 · Bagrodia Group OF Companies
A H Avenue
possession by Dec 2026 · A.h. Constructions
A. H. Heights
possession by Dec 2027 · A.h. Constructions
A.n. Heights
declared completion Apr 2026 · H Square Builders
A1 Complex
declared completion Mar 2024 · A.1. Real Estate

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026