A AND O PALAZZIO

Natwar Nagar, Jogeshwari East · ASHAPURA OPTIONS PRIVATE LIMITED

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Jul 2019declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Jul 2019

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800002732

Delivery and registration

When is the project declared for completion?

A AND O PALAZZIO is registered with MahaRERA as P51800002732 and the promoter has declared completion for 31 Jul 2019.

31 Jul 2019

declared completion

86months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800002732
Registered on04 Aug 2017
Promoter-declared completion31 Jul 2019
Current statusCertificate Signed
Against todayabout 86 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for A AND O PALAZZIO record 9 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • NCLT / insolvency — the promoter is (or was) before the NCLT for insolvency — the gravest RERA flag; buyer money and possession are at real risk.
  • Filing progress reports — 9 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Ashapura Options is the promoter of record on 58 projects registered with MahaRERA, 5 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

58projects

registered with MahaRERA

5flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for A AND O PALAZZIO in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+11.

BuildingWingsFloorsDeclared completion
A AND O PALAZZIO - A AND B WING1G+1125 Nov 2018

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 2 times, as recorded on the register.

FromExtended toStated reason
as registered31 Jul 2019The Promoter has completed the construction of the project and obtained part Occupancy Certificate on 27.11.2017, however the Occupancy Certificate (OC) of two flats viz. Flat no.1
31 Jul 201931 Jul 2019The Promoter has obtained Part OC for the Projects A&O Palazzio vide the certificate dated 27.11.2017 however OC of Two flats which are more particularly stipulated in the Part OC

Location, Land & Connectivity

Located at Natwar Nagar, Jogeshwari East, A/B Road no. 5, Kurla, Mumbai Suburban, 400060. Per the filed land record, the plot is bounded to the north by CTS 319K, to the south by CTS 270Apt-270A -23 to 28 and 33 to 67, to the east by CTS 269pt and to the west by CTS 263A-DP ROAD. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~2 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Andheri MIDC / SEEPZ2 km
Chhatrapati Shivaji Int'l Airport5 km
Powai / Hiranandani business park5 km
Bandra Kurla Complex (BKC)7 km
Lower Parel / Worli business district15 km
Nariman Point / Fort23 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Jogeshwari East

Prem Builders
possession by Oct 2026 · Prem Builders
Aim Heritage
possession by Dec 2026 · M/s Aim Realtors Private Limited
AIM Paradise
possession by Dec 2026 · S.k. Enterprises
Avant Heritage - III
possession by Dec 2026 · Avant Heritage III Realty Pvt. Ltd.
Devbhoomi
possession by Dec 2026 · Metro Capital
Iifl Centre
Developer in insolvency (NCLT) · possession by Dec 2026 · Spenta Sun City Private Limited

Major developers building in Jogeshwari East

Other RERA-registered projects in Mumbai Suburban

A H Atlantis
possession by Dec 2030 · Bagrodia Group OF Companies
A H Avenue
possession by Dec 2026 · A.h. Constructions
A. H. Heights
possession by Dec 2027 · A.h. Constructions
A.n. Heights
declared completion Apr 2026 · H Square Builders
A1 Complex
declared completion Mar 2024 · A.1. Real Estate
Aabiel Avenue
declared completion Dec 2022 · Right Channel Construction PVT LTD

What to verify (NCLT insolvency)

  1. Check the IRP/Resolution Professional's name on the NCLT cause list and contact them for a project status update.
  2. Verify whether a Resolution Plan has been approved — the IRP's report is filed with NCLT and is public.
  3. Look for a homebuyers' association for this project — allottee groups have legal standing in insolvency proceedings.
  4. Consult a RERA or IBC advocate about your rights under Section 7 IBC or Section 18 RERA for possession or refund.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026