MahaRERA Property Intelligence · Mumbai Suburban

ALAG STELLA

P51800018925 · MULUND EAST · promoter Alag Property Constructions

Certificate SignedDue 30 Jun 2022

Delivery & Registration

MahaRERA registrationP51800018925
Registered on17 Dec 2018
Promoter-declared completion30 Jun 2022
Current statusCertificate Signed
Against todayabout 49 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Alag Property Constructions is the promoter of record on 14 projects, of which 1 carries a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8.

BuildingWingsFloorsDeclared completion
ALAG STELLA1G+831 Dec 2020

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
30 Jun 202130 Jun 2022THE PROJECT HAS BEEN DELAYED DUE TO UNAVAILABILITY OF MATERIAL, LABOUR DUE TO COVID-19 PANDEMIC INDUCED LOCKDOWN.

Location, Land & Connectivity

Located at MULUND EAST, G V SCHEME ROAD NO 4, Kurla, Mumbai Suburban, 400081. Per the filed land record, the plot is bounded to the north by CTS NO 692, to the south by CTS NO 687, to the east by CTS NO 690 and to the west by G V SCHEME ROAD NO 4. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~8 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Powai / Hiranandani business park8 km
Andheri MIDC / SEEPZ10 km
Chhatrapati Shivaji Int'l Airport13 km
Bandra Kurla Complex (BKC)15 km
Lower Parel / Worli business district23 km
Nariman Point / Fort31 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Alag Property Constructions Pvt. Ltd. is the promoter on 5 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by Alag Property Constructions Pvt. Ltd.

Alag Property Constructions Pvt. Ltd.
FlaggedMumbai Suburban
Alag Property Constructions Pvt. Ltd.
FlaggedMumbai Suburban
Alag Property Constructions Pvt. Ltd.
Not filing quarterly progress reportsMumbai Suburban
Alag Property Constructions Pvt. Ltd.
FlaggedMumbai Suburban

Other RERA-registered projects in Mulund East

Abundance
possession by Sep 2026 · Goodwill Developers
Jagdale Giriraj
possession by Sep 2026 · Jagdale Infrastructure Pvt. Ltd.
Richmond Ananya
possession by Sep 2026 · Divine Enterprises
Mithagar Road Ekta Chsl
possession by Dec 2026 · Palan Realty Private Limited
Bimal Apartment Chsl
possession by Dec 2026 · Rite Builders & Developers
Govind Prakash SRA CHS LTD
possession by Dec 2026 · Omsai Developers

Major developers building in Mulund East

Other RERA-registered projects in Mumbai Suburban

Alankar
declared completion Jun 2025 · Rohinton Mehta Constructions Mumbai
Alcove Wing A
declared completion Jun 2024 · Mahindra Lifespace Developers Limited
Alcove Wing B
declared completion Jun 2024 · Mahindra Lifespace Developers Limited
Alena Residency Commercial
possession by Dec 2027 · Hemant Vinaykant Parikh
Alexio Apartment Chsl
declared completion Sep 2019 · M. Mamtora Associates
Alfa CO-Operative Housing Society LTD
possession by Dec 2027 · THE Green Venturez Developers

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026