MahaRERA Property Intelligence · Palghar

ANCHAL GALAXY

P99000021893 · KELVE EAST · promoter Cloris Construction Private

Certificate SignedDue 28 Aug 2023

Delivery & Registration

MahaRERA registrationP99000021893
Registered on08 Aug 2019
Promoter-declared completion28 Aug 2023
Current statusCertificate Signed
Against todayabout 35 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+4.

BuildingWingsFloorsDeclared completion
ANCHAL GALAXY BUILDING NO 2 WING E1G+431 Aug 2023

Complaints & Orders

1 complaint is on the MahaRERA record for this project, with orders passed in 1. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC00600000019791506/08/2021YASIRA M YASIN DODIYA vs RAJESH DAYARAM YADAVorder passed

Location, Land & Connectivity

Located at KELVE EAST, KELVE ROAD, Vasai, Palghar, 401401. Per the filed land record, the plot is bounded to the north by GUT NO 193 GOANTHAN, to the south by GUT NO 43 AND 142, to the east by GUT NO 1 AND 41 and to the west by GUT NO 44. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~140 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park140 km
Andheri MIDC / SEEPZ141 km
Chhatrapati Shivaji Int'l Airport145 km
Bandra Kurla Complex (BKC)147 km
Lower Parel / Worli business district156 km
Nariman Point / Fort163 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Kelve East

Karrm Brahmaand Affordable Homes PVT LTD
Not filing quarterly progress reports · possession by Dec 2026 · Karrm Brahmaand Affordable Homes Private
Bhaskar Save Nagar
possession by Dec 2026 · Sai Builders And Developers
Radha Residency
possession by Dec 2026 · S. S. Enterprises
Rose Heights
possession by Dec 2026 · Mehandi Hasan Sarif Shalmani
Savera Complex
Not filing quarterly progress reports · possession by Dec 2026 · Savera Builders & Developers
Shree Ganesh Complex
possession by Dec 2026 · MSD Shivay Enterprise LLP

Other RERA-registered projects in Palghar

Angel
declared completion Jun 2022 · Gita Dhiraj Chovtiya
Angel Business Centre
declared completion Jun 2023 · Angel Developers
Angel Crescenta
possession by Jun 2027 · JD Infra
Angel Homes
possession by Dec 2029 · Shreenathji Developers
Angel Landmark
declared completion Mar 2018 · Shree Vimalnath Infra
Angel Nest
possession by Dec 2027 · Thomas Albert Rodrigues

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026