Mumbai/Project record

MahaRERA · the public record

ANU-SMERA RESIDENCES

Chembur · BALAN & CHHEDA DEVELOPERS PRIVATE LIMITED

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Dec 2018declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2018

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800012341

Delivery and registration

When is the project declared for completion?

ANU-SMERA RESIDENCES is registered with MahaRERA as P51800012341 and the promoter has declared completion for 31 Dec 2018.

31 Dec 2018

declared completion

93months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800012341
Registered on01 Sep 2017
Promoter-declared completion31 Dec 2018
Current statusCertificate Signed
Against todayabout 93 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for ANU-SMERA RESIDENCES record 6 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 6 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Balan Chheda Developers is the promoter of record on 16 projects registered with MahaRERA, none of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

16projects

registered with MahaRERA

0flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for ANU-SMERA RESIDENCES in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+23.

BuildingWingsFloorsDeclared completion
SANT GADGE MAHARAJ1G+1531 Dec 2018
ANU-SMERA RESIDENCES1G+2331 Dec 2018

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Legal & Litigation

The promoter has declared 2 court cases on this project to MahaRERA. 1 is still pending. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your home. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
City Civil CourtSU 2981/20132013Pending
High Court2410 OF 20152015Dismissed

Location, Land & Connectivity

Located at Chembur, Kurla, Mumbai Suburban, 400071. Per the filed land record, the plot is bounded to the north by EXISTING ROAD, to the south by N G ACHARYA MARG, to the east by EXISTING ROAD and to the west by CST 26 PART 27 PART. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~4 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Bandra Kurla Complex (BKC)4 km
Chhatrapati Shivaji Int'l Airport6 km
Powai / Hiranandani business park7 km
Andheri MIDC / SEEPZ9 km
Lower Parel / Worli business district11 km
Nariman Point / Fort17 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Chembur

Gurukripa
possession by Sep 2026 · Inspira Realty And Infra Private Limited
Kranti Heights
possession by Sep 2026 · Sidhivinayak Constructions
Mass Metropolis
possession by Sep 2026 · Grace Urban Development Corporation
Mohite Mrugank
possession by Sep 2026 · Mohite Infraprojects Private Limited
Laxmina Krishna Niwas
possession by Oct 2026 · Laxmina Argentum Realties Private Lim
Safal SAI AND Safal Sainath
possession by Oct 2026 · Mangalnath Developers PVT LTD

Major developers building in Chembur

Other RERA-registered projects in Mumbai Suburban

Anubhuti Sadan Chsl
possession by Dec 2027 · APN India Realty LLP
Anupam Villa Chsl
declared completion Dec 2025 · M E Infraprojects PVT LTD
Anupama
possession by Mar 2028 · Shree Krishna Majestic LLP
Anuraj CO-Operative Housing Society Limited
declared completion Sep 2025 · Samarpan Homes & Developers
Anusaya
possession by Jun 2027 · Satre Infrastructure Pvt. Ltd.
Anushree Apartment
declared completion Aug 2023 · Esmech Rolling Machinery LLP

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026