Mumbai/Project record

MahaRERA · the public record

ANWAR MANSION

DHOVALI · ABRAR ANWAR PATEL

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 May 2026declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 May 2026

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P99000031514

Delivery and registration

When is the project declared for completion?

ANWAR MANSION is registered with MahaRERA as P99000031514 and the promoter has declared completion for 31 May 2026.

31 May 2026

declared completion

4months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP99000031514
Registered on25 Oct 2021
Promoter-declared completion31 May 2026
Current statusCertificate Signed
Against todayabout 4 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for ANWAR MANSION record 19 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • QPR non-compliance — flagged by MahaRERA for not filing its mandatory quarterly progress reports.
  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Promoter record

What else is this promoter on record for?

Abrar Anwar Patel is the promoter of record on 2 projects registered with MahaRERA, 1 of which carries a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

2projects

registered with MahaRERA

1flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for ANWAR MANSION in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+5.

BuildingWingsFloorsDeclared completion
ANWAR MANSION1G+531 May 2026

Legal and disputes

What disputes are disclosed?

1 complaint is on the MahaRERA record for ANWAR MANSION, with orders passed in 1 of them.

1complaint

1with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC1250161918/05/2025MOHAMED NAYYAR GULAM MISHAL vs ABRAR ANWAR PATELorder passed

Location, Land & Connectivity

Located at DHOVALI, DHOVALI, Vasai, Palghar, 401207. Per the filed land record, the plot is bounded to the north by ROAD, to the south by ROAD, to the east by JAMA MASJID TRUST and to the west by ROAD. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Papdy

Nilkant Sadan
possession by Dec 2026 · Divija Developers
SKY Vista
possession by Dec 2026 · M/s. Divine Construction
Redevelopment Of Chinmay Co-Operative Housing Society Ltd
possession by Jan 2027 · Neom Construction
Premier Elegance
possession by Mar 2027 · Premear Landmark Developers LLP
Angel Crescenta
possession by Jun 2027 · JD Infra
Palacia
possession by Aug 2027 · M/s. Sagar Developers

Other RERA-registered projects in Palghar

Apeksha Complex
possession by Dec 2026 · Kothari Construction CO
Apeksha Imperial
declared completion Dec 2020 · Shree RAM Builders AND Developers
Apex Wildernest
declared completion Mar 2019 · Apex Creators
Aqsa Building 2
possession by Dec 2026 · NEW Star Developers Aqsa Building 2
Aradhya Heights
possession by Dec 2026 · Harshal Pandit Khairnar
Aradhya Residency
possession by Mar 2027 · Devine Infra

What to verify (QPR non-filer)

  1. Cross-check the developer's last QPR filing date on the MahaRERA portal — non-filing can indicate stalled construction.
  2. Visit the site (or request a third-party inspection report) to verify actual construction progress.
  3. If no QPR has been filed for more than two quarters, file a complaint with MahaRERA for non-disclosure.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026