APEKSHA IMPERIAL

Thane · SHREE RAM BUILDERS AND DEVELOPERS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Dec 2020declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2020

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P99000003014

Delivery and registration

When is the project declared for completion?

APEKSHA IMPERIAL is registered with MahaRERA as P99000003014 and the promoter has declared completion for 30 Dec 2020.

30 Dec 2020

declared completion

69months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP99000003014
Registered on04 Aug 2017
Promoter-declared completion30 Dec 2020
Current statusCertificate Signed
Against todayabout 69 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for APEKSHA IMPERIAL record 14 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 14 quarterly progress reports on record since registration, with no current default.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for APEKSHA IMPERIAL in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+4.

BuildingWingsFloorsDeclared completion
APEKSHA IMPERIAL1G+4-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered30 Dec 2020Construction work completed. Occupation Certificate not received. delay from Competent authority.

Location, Land & Connectivity

Located at Thane, Thane, 401208. Per the filed land record, the plot is bounded to the north by H1 28, to the south by RG, to the east by RG and to the west by RG. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~26 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Andheri MIDC / SEEPZ26 km
Powai / Hiranandani business park28 km
Chhatrapati Shivaji Int'l Airport30 km
Bandra Kurla Complex (BKC)33 km
Lower Parel / Worli business district41 km
Nariman Point / Fort49 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

See every Shree RAM Builders AND Developers project & its RERA track record →

Other RERA-registered projects in Vasai East

AAI Chandika Hills
possession by Sep 2026 · Shivam Builders & Developers
Dreams Heights Building NO- I
possession by Sep 2026 · Lodha Builders AND Developers
Trinity Oasis
possession by Sep 2026 · Harsh Tirupati Developers LLP
Matoshri Heights
possession by Oct 2026 · Nagesh Hemant Patil
Hayaat Galaxy II
possession by Nov 2026 · M M Enterprises
Apeksha Complex
possession by Dec 2026 · Kothari Construction CO

Major developers building in Vasai East

Other RERA-registered projects in Palghar

Apex Wildernest
declared completion Mar 2019 · Apex Creators
Aqsa Building 2
possession by Dec 2026 · NEW Star Developers Aqsa Building 2
Aradhya Heights
possession by Dec 2026 · Harshal Pandit Khairnar
Aradhya Residency
possession by Mar 2027 · Devine Infra
Arafat CHS Ltd,anab CHS Ltd, AL Ashiyana CHS LTD
possession by Dec 2027 · Karari Group Builders & Developers
Arch Developers
possession by Mar 2027 · Arch Developers

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026