MahaRERA Property Intelligence · Palghar

ARADHYA RESIDENCY

P99000026640 · KELWA · promoter Devine Infra

Certificate SignedDue 31 Mar 2027

Delivery & Registration

MahaRERA registrationP99000026640
Registered on12 Oct 2020
Promoter-declared completion31 Mar 2027
Current statusCertificate Signed
Against today8 months to the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+3.

BuildingWingsFloorsDeclared completion
WING A1G+331 Mar 2021
WING B1G+331 Mar 2021

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
30 Jun 202331 Mar 2027DUE TO COVID-19 AND PERMISSION DELAY THE PROJECT WAS NOT ABLE TO GET COMPLETED ON TIME. WE WOULD LIKE TO REQUEST YOU TO FURTHER GRANT US EXTENSION TILL 31/03/2027

Location, Land & Connectivity

Located at KELWA, PATIL PADA, Borivali, Mumbai Suburban, 401401. Per the filed land record, the plot is bounded to the north by PLOT NO 11, to the south by PLOT NO 7, to the east by GUT NO 40 B PART and to the west by 6 M WIDE LAYOUT ROAD. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Kelve East

Karrm Brahmaand Affordable Homes PVT LTD
Not filing quarterly progress reports · possession by Dec 2026 · Karrm Brahmaand Affordable Homes Private
Bhaskar Save Nagar
possession by Dec 2026 · Sai Builders And Developers
Radha Residency
possession by Dec 2026 · S. S. Enterprises
Rose Heights
possession by Dec 2026 · Mehandi Hasan Sarif Shalmani
Savera Complex
Not filing quarterly progress reports · possession by Dec 2026 · Savera Builders & Developers
Shree Ganesh Complex
possession by Dec 2026 · MSD Shivay Enterprise LLP

Other RERA-registered projects in Palghar

Arafat CHS Ltd,anab CHS Ltd, AL Ashiyana CHS LTD
possession by Dec 2027 · Karari Group Builders & Developers
Arch Developers
possession by Mar 2027 · Arch Developers
Arham Residency
declared completion Dec 2025 · NPS Buildcon Private Limited
Arham Villas
declared completion Mar 2022 · Vasudha Builders Limited
Ariana
possession by Mar 2027 · Mansarovar Estate Builders LLP
Arihant Apartment
declared completion Jan 2020 · Rishabh Sandeep Tiwari

What to verify (QPR non-filer)

  1. Cross-check the developer's last QPR filing date on the MahaRERA portal — non-filing can indicate stalled construction.
  2. Visit the site (or request a third-party inspection report) to verify actual construction progress.
  3. If no QPR has been filed for more than two quarters, file a complaint with MahaRERA for non-disclosure.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.