Mumbai/Project record

MahaRERA · the public record

Aristo Classic

Mumbai Suburban · AOP OF BINDESH AND MILIND SOMAIYA

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Oct 2024declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Oct 2024

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800010913

Delivery and registration

When is the project declared for completion?

Aristo Classic is registered with MahaRERA as P51800010913 and the promoter has declared completion for 31 Oct 2024.

31 Oct 2024

declared completion

23months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800010913
Registered on31 Aug 2017
Promoter-declared completion31 Oct 2024
Current statusCertificate Signed
Against todayabout 23 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Aristo Classic record 30 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 30 quarterly progress reports on record since registration, with no current default.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Aristo Classic in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+12.

BuildingWingsFloorsDeclared completion
Aristo Classic1G+1230 Jun 2021

Legal and disputes

What disputes are disclosed?

2 complaints are on the MahaRERA record for Aristo Classic, with orders passed in 1 of them.

2complaints

1with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000037507015/04/2023Rohini Purshottam Khedekar vs AOP OF BINDESH & MILIND SOMAIYApending / no order on file
CC00600000039555315/05/2023Prashant Nilkanth Manohar vs AOP Of Bindesh & Milind Somaiyaorder passed

Legal & Litigation

The promoter has declared 3 court cases on this project to MahaRERA. 3 are still pending. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your home. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Court Of Small Causes198/4062014Pending
Court Of Small Causes4522014Pending
High Court8062016Pending

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 3 times, as recorded on the register.

FromExtended toStated reason
as registered30 Dec 2020We have Real Estate project registered with MahaRERA authority with name “Aristo Classic” vide Certificate No. P51800010913 dated 31/08/2017. Due date for the completion of the pro
30 Dec 202030 Jun 2022I, hereby apply for extension u/s 7(3) of the registered project bearing vide no P51800010913. The end date of the project is 30th June 2021, I wish to extend the project till 30th
30 Jun 202231 Oct 2024As per the attachment

Location, Land & Connectivity

Located at Borivali, Mumbai Suburban, 400064. Per the filed land record, the plot is bounded to the north by Turel Pakhadi Road, to the south by Zakeria Road, to the east by CTS NO 563 and to the west by CTS NO 525 AND 530. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~7 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Andheri MIDC / SEEPZ7 km
Powai / Hiranandani business park10 km
Chhatrapati Shivaji Int'l Airport11 km
Bandra Kurla Complex (BKC)13 km
Lower Parel / Worli business district21 km
Nariman Point / Fort29 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Malad West

Shree Hari Krupa
possession by Sep 2026 · Mamtora Foundation
Shreeji Plaza Wing B
possession by Sep 2026 · Siddharth Enterprises
Linkpark
possession by Oct 2026 · Adarsh Industrial Estate Private Limited
Bhagat Grandeur
possession by Dec 2026 · Chirag Agro Fins Private Limited
Liberty Heights
possession by Dec 2026 · VP Casa Constructions LLP
Lovely Chs. LTD
possession by Dec 2026 · Jinam Realtors

Major developers building in Malad West

Other RERA-registered projects in Mumbai Suburban

Aristocrate
possession by Dec 2027 · Amit Sudhir Dhadda
Arkade Ascend
possession by Jun 2031 · Arkade Developers Limited
Arkade Earth-Carnation
declared completion Dec 2024 · Arkade Developers Private Limited
Arkade Earth-Daffodil
declared completion Dec 2023 · Arkade Developers Private Limited
Arkade Earth - Hazel
declared completion Dec 2023 · Arkade Developers Private Limited
Arkade Eden
possession by Dec 2026 · Arkade Developers Limited

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026