MahaRERA Property Intelligence · Mumbai Suburban

ASHWIN HEIGHTS

P51800056243 · GOREGAON MUMBAI · promoter Westinrely Developers Pvt

Certificate SignedDue 31 Dec 2026

Delivery & Registration

MahaRERA registrationP51800056243
Registered on22 May 2024
Promoter-declared completion31 Dec 2026
Current statusCertificate Signed
Against today5 months to the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Construction Progress

MahaRERA's cost filing puts construction at ~61.0% of the estimated project cost incurred as of the last certificate (₹6.46 Cr spent against a ₹10.60 Cr estimate). This financial % is the regulator's own proxy for how much is physically built — the closest public read on real progress, and one a brochure never shows.

Cost-incurred % as last certified to MahaRERA; it can lag on-site reality between filings. Confirm the current stage and the latest Form 2 before you book.

Sales & Inventory

Of 10 homes filed with MahaRERA, 0 are sold/booked and 10 remain available (~0% sold) — early in sales — more choice of units now, but confirm the developer has the pre-sales to fund the build. Note: the project registers 37 homes in total, but this sold/unsold inventory filing covers only 10 of them — the other 27 aren't in the ledger yet. Ask the builder what they are (an unreleased phase, held-back stock, or non-saleable/car-park units) before reading too much into the percentage. This is the promoter's own reported inventory as at the last compliance filing; confirm current availability directly.

The unsold units on the filing — if you're quoted a unit NOT on this list, ask why it shows as sold/booked on the RERA record:

FloorUnitCarpetReckoner value
Floor 101002557 sqft (51.76 sqm)₹81.45 Lakh
Floor 111101412 sqft (38.31 sqm)₹60.29 Lakh
Floor 111102557 sqft (51.76 sqm)₹81.45 Lakh
Floor 111103601 sqft (55.79 sqm)₹87.80 Lakh
Floor 111201561 sqft (52.13 sqm)₹82.04 Lakh
Floor 2203601 sqft (55.79 sqm)₹87.80 Lakh
Floor 3302441 sqft (40.94 sqm)₹64.43 Lakh
Floor 5501412 sqft (38.31 sqm)₹60.29 Lakh
Floor 9901412 sqft (38.31 sqm)₹60.29 Lakh
Ground/Floor 0GroundOffice732 sqft (67.96 sqm)₹1.23 Cr

⚠ The inventory filing also declares: 14 reserved. Before booking, confirm YOUR unit appears in none of these lists and get any lender NOC in writing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+14 and 37 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
ASHWIN HEIGHTS1G+1437-

Unit mix on the filing: 34 residential and 3 non-residential (shops/offices).

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at GOREGAON MUMBAI, AAREY ROAD, Andheri, Mumbai Suburban, 400063. Per the filed land record, the plot is bounded to the north by ARRAY ROAD, to the south by CTS NO 296 AND 299, to the east by CTS NO 296 and to the west by CTS NO 298. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~5 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Andheri MIDC / SEEPZ5 km
Powai / Hiranandani business park8 km
Chhatrapati Shivaji Int'l Airport8 km
Bandra Kurla Complex (BKC)11 km
Lower Parel / Worli business district18 km
Nariman Point / Fort27 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Goregaon East

Matrusmruti
possession by Oct 2026 · Gio Properties
Samarth Nandadeep Heights
possession by Oct 2026 · Samarth Tsquare
Onyx
possession by Nov 2026 · Shreeram Builders
Goregaon Adwait Chsl - Vijay Sadan
possession by Dec 2026 · Prashant Shirsat
Agarwal Floresta - Maple
possession by Dec 2026 · Homewell Realty LLP
Avant Hillway, Composite Building - B1 Sale Wing, Sapphire
possession by Dec 2026 · Raghvendra Construction Company PVT LTD

Major developers building in Goregaon East

Other RERA-registered projects in Mumbai Suburban

Ashwini Elite
declared completion Dec 2024 · Ashok H Tharwani
Ashwini Residency Borivali Ashwini Chsl
declared completion Dec 2019 · Ethics Infra Development Pvt Ltd
Asiad
declared completion Oct 2024 · Asiad Housing AND Property Development S
Asian Nirmal
possession by Jun 2028 · Maniar Asian Infra LLP
Asma Enclave
possession by Dec 2029 · Faith K S Infra LLP
Asmi
declared completion Dec 2019 · Sia Developers LLP

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026