Mumbai/Project record

MahaRERA · the public record

Lodha Fiorenza

Goregaon East · LODHA DEVELOPERS LIMITED

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Jan 2018declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Jan 2018

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800000195

Delivery and registration

When is the project declared for completion?

Lodha Fiorenza is registered with MahaRERA as P51800000195 and the promoter has declared completion for 31 Jan 2018.

31 Jan 2018

declared completion

104months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800000195
Registered on10 Jul 2017
Promoter-declared completion31 Jan 2018
Current statusCertificate Signed
Against todayabout 104 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Lodha Fiorenza record 3 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 3 quarterly progress reports on record since registration, with no current default.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Lodha Fiorenza in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+44.

BuildingWingsFloorsDeclared completion
ROMA1G+4431 Jan 2018
MILANO1G+3631 Jan 2018

Legal and disputes

What disputes are disclosed?

5 complaints are on the MahaRERA record for Lodha Fiorenza, with orders passed in 5 of them.

5complaints

5with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000000089326/09/2017SATISH WAGH vs LODHA DEVELOPERS PRIVATE LIMITEDorder passed
CC00600000007819121/02/2019Lal Bahadur Singh and Anr vs Lodha Developers Limitedorder passed
CC00600000005526406/07/2018VISHAL REALMART PVT LTD (DIRECTOR ARPIT MITTAL) vs LODHA PRANIK LANDMARK DEVELOPERS PRIVATE LIMITEDorder passed
CC00600000005578923/08/2018Pratibha Fabrics Limited vs Lodha Developers Private Limitedorder passed
CC00600000005580423/08/2018Spectrum Dyes and Chemicals Private Limited vs Lodha Developers Private Limited & Anotherorder passed

Legal & Litigation

The promoter has declared 2 court cases on this project to MahaRERA. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your home. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Bombay High Court332017Pre Admission Not Updated
Delhi High Court1292018Hearing

Location, Land & Connectivity

Located at Goregaon East, Western Express Highway, Mumbai City, Mumbai City, 400063. Per the filed land record, the plot is bounded to the north by 12 M W Layout road CS no 586-2, to the south by Proposed 35 M W DP road, to the east by Sienna and western express highway and to the west by 12 M W Layout road CS no 586-3. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~4 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Andheri MIDC / SEEPZ4 km
Powai / Hiranandani business park8 km
Chhatrapati Shivaji Int'l Airport8 km
Bandra Kurla Complex (BKC)11 km
Lower Parel / Worli business district19 km
Nariman Point / Fort27 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Lodha Developers Limited is the promoter on 171 MahaRERA-registered projects, of which 9 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

See every Lodha Developers Limited project & its RERA track record →

Other flagged projects by Lodha Developers Limited

Lodha Developers Limited
FlaggedThane
Lodha Developers Limited
FlaggedThane
Lodha Developers Limited
FlaggedThane
Lodha Developers Limited
FlaggedThane
Lodha Developers Limited
FlaggedThane
Lodha Developers Limited
FlaggedThane

Other RERA-registered projects in Goregaon East

Matrusmruti
possession by Oct 2026 · Gio Properties
Samarth Nandadeep Heights
possession by Oct 2026 · Samarth Tsquare
Onyx
possession by Nov 2026 · Shreeram Builders
Goregaon Adwait Chsl - Vijay Sadan
possession by Dec 2026 · Prashant Shirsat
Agarwal Floresta - Maple
possession by Dec 2026 · Homewell Realty LLP
Ashwin Heights
possession by Dec 2026 · Westinrely Developers PVT LTD

Major developers building in Goregaon East

Other RERA-registered projects in Mumbai Suburban

Lodha Kandivali Project-Tower 1
possession by Feb 2028 · Lodha Developers Limited
Lodha Kandivali Project - Tower 2
declared completion Dec 2025 · Macrotech Developers Limited
Lodha Kandivali Project - Tower 2
declared completion Jul 2026 · Lodha Developers Limited
Lodha Kandivali Project - Tower 3
declared completion Jun 2026 · Lodha Developers Limited
Lodha Kandivali Project - Tower 4
declared completion May 2025 · Macrotech Developers Limited
Lodha Kandivali Project - Tower 5
declared completion Jul 2026 · Lodha Developers Limited

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026