AVD AVADH

kamatghar · AVD INFRA INDIA PRIVATE LIMITED

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Sep 2022declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Sep 2022

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51700013756

Delivery and registration

When is the project declared for completion?

AVD AVADH is registered with MahaRERA as P51700013756 and the promoter has declared completion for 30 Sep 2022.

30 Sep 2022

declared completion

48months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51700013756
Registered on25 Oct 2017
Promoter-declared completion30 Sep 2022
Current statusCertificate Signed
Against todayabout 48 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for AVD AVADH record 20 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 20 quarterly progress reports on record since registration, with no current default.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for AVD AVADH in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+9.

BuildingWingsFloorsDeclared completion
AVD AVADH1G+930 Sep 2020

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 2 times, as recorded on the register.

FromExtended toStated reason
as registered29 Sep 2021DUE TO CHANGE IN DEVELOPMENT RULE WE HAVE APPLIED FOR ADDITIONAL APPROVALS, AND WE ARE EXPECTING APPROVALS SHORTLY, AND TO COMPLETE THIS WORK WE WILL NEED ADDITIONAL ONE YEAR
29 Sep 202130 Sep 2022Due to Unforeseen circumstances the project got delayed

Location, Land & Connectivity

Located at kamatghar, kamatghar, Borivali, Mumbai Suburban, 421302. Per the filed land record, the plot is bounded to the north by Survey No 141, to the south by Survey No 136-8 Part, to the east by Survey No 136-8 Part and to the west by 30 Mtr wide DP. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~23 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park23 km
Andheri MIDC / SEEPZ25 km
Chhatrapati Shivaji Int'l Airport28 km
Bandra Kurla Complex (BKC)30 km
Lower Parel / Worli business district39 km
Nariman Point / Fort46 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Bhiwandi

Nazir Heights
possession by Sep 2026 · A M Constructions
Rose Residency
possession by Sep 2026 · Kunal Ramesh Karaniya
Saniya Heights
possession by Sep 2026 · Moonshine Realtors PVT LTD
Upper Thane-Casa Eden
possession by Sep 2026 · Lodha Developers Limited
Anantam Heights
possession by Oct 2026 · Kanak Realty
Upper Thane - Woodlands A, B AND J
possession by Oct 2026 · Lodha Developers Limited

Major developers building in Bhiwandi

Other RERA-registered projects in Thane

Avdhut
possession by Dec 2026 · S.k. Homes Builder & Developers
Avenue
possession by Dec 2028 · Buildbrick Builders AND Developers
Aveon City Building B
possession by Dec 2032 · Balaji Tricity Realty LLP
Avesa
possession by Oct 2026 · Jagdale Infrastructure Pvt. Ltd.
Avighna Building NO 3
possession by Dec 2026 · Chheda Developments
Avighna Building No 4
possession by Dec 2027 · Chheda Developments

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026