BALAJI VIVANTA

P51700029805 · KALYAN · promoter Mayur Enterprises Builders

Certificate SignedDue 31 Dec 2023

Delivery & Registration

MahaRERA registrationP51700029805
Registered on04 Jul 2021
Promoter-declared completion31 Dec 2023
Current statusCertificate Signed
Against todayabout 31 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Mayur Enterprises Builders is the promoter of record on 55 projects, of which 10 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8.

BuildingWingsFloorsDeclared completion
MERCURY1G+831 Dec 2023

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at KALYAN, KALYAN, Ulhasnagar, Thane, 421103. Per the filed land record, the plot is bounded to the north by PROPERTY OF OLD SURVEY NO 69 AND BALAJI PLACE, to the south by PROPERTY OF RADHA KRISHNA NAGAR CHAWL PART OFSNO72, to the east by PROPERTY OF BALIRAM MHATRE AND SHRICHAND KUKREJA and to the west by SAI POOJA APT AND RAJ TOWER KONKAN. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Kalyan

Gurudev Orchid
possession by Sep 2026 · Gurudev Developers
Precious Meadows
possession by Nov 2026 · Vinayak Associates
Mahadev Heights
possession by Dec 2026 · Onbv Reality
Siddhivinayak Homes
possession by Dec 2026 · Siddhivinayak Builders AND Developers
Vasudev Laxmi Park
possession by Jan 2027 · Mahesh Manohar Salphale
Mangalmurti Heights
possession by Mar 2027 · Ramesh Nanalal Jain

Major developers building in Kalyan

Other RERA-registered projects in Thane

Balaram Elevate
possession by Mar 2030 · Shree Siddhivinayak Buildcon
Balaram Heights
possession by Sep 2027 · Shree Samarth Krupa Enterprises
Balaram Heights
possession by Dec 2029 · Ganesh Tukaram Bhane
Baliram Tare Residency
possession by Dec 2028 · Tare Group Builders AND Developers
Balkrishna CHS LTD
possession by Jun 2027 · Balkrishna CO-Operative Society Limited
Balkrushna Arcade
declared completion Sep 2021 · Shivaji Parshuram Kathore

What to verify (inactive registration)

  1. Download the MahaRERA order stating the reason for deregistration or suspension — this is public on the portal.
  2. Check whether the developer has filed a challenge in the Appellate Tribunal and whether the order is stayed.
  3. Do not make any further payments until the registration status is restored or you obtain legal advice.
  4. Contact MahaRERA's helpdesk for guidance on alternative arrangements or pending dues.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026