Mumbai/Project record

MahaRERA · the public record

BELLISSIMA

BANDRA WEST · EXCEL INFRA CONSTRUCTION LLP

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

16units filed as unsoldInventory · 19 September 2026
31 Dec 2028declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2028

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800076596

Delivery and registration

When is the project declared for completion?

BELLISSIMA is registered with MahaRERA as P51800076596 and the promoter has declared completion for 31 Dec 2028.

31 Dec 2028

declared completion

27months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800076596
Registered on18 Jun 2024
Promoter-declared completion31 Dec 2028
Current statusCertificate Signed
Against today27 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for BELLISSIMA record 12 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Promoter record

What else is this promoter on record for?

Excel Infra Construction is the promoter of record on 36 projects registered with MahaRERA, 5 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

36projects

registered with MahaRERA

5flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

What the filings record, home by home

Read from MahaRERA on 19 September 2026

MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for the sold ones the registered agreement value — the consideration filed for that specific home. On this project 17 homes carry one, and 16 of the 33 are recorded unsold.

Here is one of those unsold homes, priced against what buyers of the same home on other floors actually filed:

HomeCarpetFiled for the same home on other floorsBased on
12011,634 sqftRs 6.5360 cr typical, over Rs 5.0000 cr to Rs 7.4347 cr5 filed on this stack, floors 11–21

A filed consideration is what was registered for one home. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the home is available to you today. Only one observation of this ledger so far: no change can be reported yet.

In BELLISSIMA, 14 of the 16 unsold homes have agreements filed on their own stack. The Price Comparison Report gives each of them its own row — the filed agreements behind that stack listed in full, the government reckoner value the promoter filed against it, and whether it is mortgaged to a lender while still on the unsold list. Built from the filing itself, sent by email.

See the other 15 homes — ₹2,999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+21.

BuildingWingsFloorsDeclared completion
BELLISSIMA1G+2131 Dec 2028

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at BANDRA WEST , KRISHEN CHANDRA MARG , Kurla, Mumbai Suburban, 400050. Per the filed land record, the plot is bounded to the north by GENERAL ARUNKUMAR VAIDYA ROAD, to the south by PLOT NO 14, to the east by 8 9 MTRS WIDE EXISTING ROAD and to the west by PLOT NO 12. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Bandra West

Bandra Boon CHS LTD
possession by Sep 2026 · Mass Jaks Associate Ventures
Aryan Tower
Not filing quarterly progress reports · possession by Dec 2026 · Suchit Developers
Brightland
possession by Dec 2026 · Sambhavparshva Developers Private Limite
Hill Casa
possession by Dec 2026 · Husain Taher Patni
Hill View
possession by Dec 2026 · L Nagpal Builders LLP
Manthan Embassy
possession by Dec 2026 · Manthan Development Corporation

Major developers building in Bandra West

Other RERA-registered projects in Mumbai Suburban

Bellissimo Mulund T2
possession by Jun 2027 · Lodha Developers Limited
Benchmark Plaza
possession by Dec 2026 · Benchmark Projects PVT LTD
Besant Arti CHS Ltd
declared completion Dec 2020 · Shamik Enterprises Pvt Ltd.
Bhagat Grandeur
possession by Dec 2026 · Chirag Agro Fins Private Limited
Bhagwan Residency
possession by Oct 2026 · V3 Partners
Bhagyawan Primrose
possession by Dec 2027 · Bhagyawati Enterprises

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026