BINDRA SATERI LEGACY C WING AND F WING PHASE II - 11TH AND ABOVE FLOORS

P51800025061 · MIDC · promoter Bindra Sateri Constructions

Certificate SignedDue 30 Dec 2023

Delivery & Registration

MahaRERA registrationP51800025061
Registered on18 Mar 2020
Promoter-declared completion30 Dec 2023
Current statusCertificate Signed
Against todayabout 31 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Bindra Sateri Constructions is the promoter of record on 4 projects, of which none currently carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+6.

BuildingWingsFloorsDeclared completion
BINDRA SATERI LEGACY C WING PHASE II - 11TH AND ABOVE FLOORS1G+631 Dec 2022
BINDRA SATERI LEGACY F WING PHASE II - 11TH AND ABOVE FLOORS1G+631 Dec 2022

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at MIDC, ROAD NO 22, Andheri, Mumbai Suburban, 400093. Per the filed land record, the plot is bounded to the north by CTS NO 24, to the south by CTS NO 69 MULGAON VILLAGE, to the east by CTS NO 26 and to the west by CTS NO 24. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Bindra Sateri Constructions is the promoter on 4 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by Bindra Sateri Constructions

Bindra Sateri Constructions
FlaggedMumbai Suburban
Bindra Sateri Constructions
FlaggedMumbai Suburban
Bindra Sateri Constructions
FlaggedMumbai Suburban

Other RERA-registered projects in Andheri East

Inspire Residency
possession by Dec 2026 · Sardar Realty
Mahakali Hills
possession by Dec 2026 · Mohid Construction Co
Royal Fantasy Phase II
possession by Dec 2026 · Royal Fantasy Constructions Private Limi
Samarth Enclave F AND G Wing Andheri Chhaya CHS
possession by Dec 2026 · Samarth Erectors AND Developers
Samarth Enclave H Wing Andheri Chhaya CHS
possession by Dec 2026 · Samarth Erectors AND Developers
Zennith
possession by Dec 2026 · Apexbliss Infraventures Private Limited

Major developers building in Andheri East

Other RERA-registered projects in Mumbai Suburban

Bindu / Vidyavihar
declared completion Dec 2018 · Not Available
Bitcon Elysium
possession by Jan 2029 · Bitcon India Infrastructure Developers P
BIZ Point
possession by Dec 2027 · N N Datar & Associates
BKC 28
declared completion Jun 2025 · Vakratunda Buildcon Private Limited
BKC 9
possession by Jul 2028 · Vakratunda Buildcon Private Limited
BKC Crown
possession by Dec 2026 · Shreeji Properties

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026