MahaRERA Property Intelligence · Mumbai Suburban
P51800014896 · ANDHERI EAST · promoter Blue Canyon Realty
| MahaRERA registration | P51800014896 |
| Registered on | 09 Jan 2018 |
| Promoter-declared completion | 29 Feb 2024 |
| Current status | Certificate Signed |
| Against today | about 29 months past the declared date |
MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.
The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8.
| Building | Wings | Floors | Declared completion |
|---|---|---|---|
| BLUE SAPPHIRE | 1 | G+8 | 30 Apr 2022 |
1 complaint is on the MahaRERA record for this project, with orders passed in 1. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.
| Complaint no. | Filed | Parties | Status |
|---|---|---|---|
| CC006000000192631 | 15/02/2020 | Mangesh Kadav vs Blue Canyon Realty Pvt Ltd | order passed |
The promoter has had the MahaRERA completion deadline formally extended 3 times. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.
| From (declared) | To (revised) | Stated reason |
|---|---|---|
| 29 Feb 2024 | 30 Oct 2021 | The construction of the said project was adversely affected due to the nationwide lockdown imposed due to the pandemic Covid-19. It was difficult to obtain raw materials for constr |
| 29 Feb 2024 | 30 Apr 2020 | Due to new DCR 2034 amended plan has to be submitted as per the UDD notification dated 21-09-2018 |
| 29 Feb 2024 | 29 Feb 2024 | In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various r |
Located at ANDHERI EAST, CHAKALA, Mumbai City, Mumbai City, 400099. Per the filed land record, the plot is bounded to the north by Bldg No 19, to the south by Tarun Bharat Internal Road, to the east by Bldg No 18 and to the west by Bldg No 16. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.
The nearest major job hub is ~2 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.
| Landmark | Straight-line |
|---|---|
| Andheri MIDC / SEEPZ | 2 km |
| Chhatrapati Shivaji Int'l Airport | 2 km |
| Powai / Hiranandani business park | 4 km |
| Bandra Kurla Complex (BKC) | 5 km |
| Lower Parel / Worli business district | 13 km |
| Nariman Point / Fort | 21 km |
Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.
🔒 The verdict & buyer playbook · Compliance report
The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.
🔒 Unit-by-unit guidance · Unit Guidance report
Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.
🔒 Full financial records — escrow, funding & the document catalog · Compliance report
The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.
Should you buy in BLUE SAPPHIRE?
This page is the free MahaRERA filing summary. The full RERA Property Intelligence Report gives you the full regulatory standing, declared court litigation, buyer-complaint and adjudication history, quarterly-progress-report discipline, the builder's MahaRERA-wide track record, the building/tower breakdown, and the sanctioned layout plan. See a real one first:
Sample: Lodha Kandivali – Tower 2 → · browse all sample reports →
Compliance Report · ₹999
The regulator’s filing record, read · 1 working day
Scan with any UPI app to pay · quietlist@kotak
Unit Guidance Report · ₹2,999
Everything, down to which unit · 1 working day
Not useful to your decision? Full refund — no questions asked.
Scan with any UPI app to pay · quietlist@kotak
Paying from outside India? Pay $15 (Compliance) or $39 (Unit Guidance) via PayPal, or email hello@quietlist.in for a card invoice. Prefer to talk first, or have a portfolio to check? Same address. An information aid for your own due diligence, not legal or investment advice.
Free · Watch this project
We'll email you when this project's RERA record changes.
Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.
Last checked against the RERA register: 27 Jul 2026