BORIVALLI SAI SUMAN

Mumbai Suburban · SARAH ENTREPRISES

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Aug 2019declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Aug 2019

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800013856

Delivery and registration

When is the project declared for completion?

BORIVALLI SAI SUMAN is registered with MahaRERA as P51800013856 and the promoter has declared completion for 30 Aug 2019.

30 Aug 2019

declared completion

85months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800013856
Registered on27 Oct 2017
Promoter-declared completion30 Aug 2019
Current statusCertificate Signed
Against todayabout 85 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for BORIVALLI SAI SUMAN record 8 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 8 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Sarah Entreprises is the promoter of record on 3 projects registered with MahaRERA, 1 of which carries a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

3projects

registered with MahaRERA

1flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for BORIVALLI SAI SUMAN in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+19.

BuildingWingsFloorsDeclared completion
WING A1G+17-
WING B1G+19-

Legal and disputes

What disputes are disclosed?

2 complaints are on the MahaRERA record for BORIVALLI SAI SUMAN, with orders passed in 2 of them.

2complaints

2with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000004400506/04/2018Shilpa Mahesh Lukhi vs Borivali Sai Suman CHS Ltd.order passed
CC00600000021004522/02/2022Nilesh R Mangukiya & Ors members of prop association as per Exh A vs Borivali Sai Suman CHSorder passed

Legal & Litigation

The promoter has declared 22 court cases on this project to MahaRERA. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your home. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
City Civil Dindoshi Mumbai11602015Being Adjudecated
City Civil Dindoshi Mumbai11612015Being Adjudecated
City Civil Dindoshi Mumbai11622015Being Adjudecated
City Civil Dindoshi Mumbai11632015Being Adjudecated
City Civil Dindoshi Mumbai11642015Being Adjudecated
City Civil Dindoshi Mumbai11652015Being Adjudecated
City Civil Dindoshi Mumbai11662015Being Adjudecated
City Civil Dindoshi Mumbai11672015Being Adjudecated
City Civil Dindoshi Mumbai11682015Being Adjudecated
City Civil Dindoshi Mumbai11692015Being Adjudecated
City Civil Dindoshi Mumbai11812015Being Adjudecated
City Civil Dindoshi Mumbai12582015Being Adjudecated
City Civil Dindoshi Mumbai12592015Being Adjudecated
City Civil Dindoshi Mumbai12602015Being Adjudecated
City Civil Dindoshi Mumbai12612015Being Adjudecated
City Civil Dindoshi Mumbai12622015Being Adjudecated
City Civil Dindoshi Mumbai12632015Being Adjudecated
City Civil Dindoshi Mumbai12642015Being Adjudecated
City Civil Dindoshi Mumbai13132015Being Adjudecated
City Civil Dindoshi Mumbai13142015Being Adjudecated
City Civil Court At Mumbai Borivalli Division Dindoshi Goregaon MumbaiSUIT NO 1797 0F 20162016Adjudecated
Bombay High Court8842018Being Adjudecated

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered30 Aug 2019due to litigation with purchasers of open sale and tenants for rent compensation amount project has been delayed

Location, Land & Connectivity

Located at Andheri, Mumbai Suburban, 400103. Per the filed land record, the plot is bounded to the north by CTS NO 2386, to the south by CTS NO 2247, to the east by CTS NO 2246 and to the west by CTS NO 2249. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~13 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Andheri MIDC / SEEPZ13 km
Powai / Hiranandani business park15 km
Chhatrapati Shivaji Int'l Airport17 km
Bandra Kurla Complex (BKC)20 km
Lower Parel / Worli business district28 km
Nariman Point / Fort36 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Borivali West

Borivali Madhumas Chsl
possession by Dec 2026 · Aadhunik Developers
Borivali SAI Hill CHS
possession by Dec 2026 · THE Green Venturez Realtors
Empire Fairmont
possession by Dec 2026 · Empire Realty
Maruti Residency
possession by Dec 2026 · OM Construction
Mascarenhas Apartment
Not filing quarterly progress reports · possession by Dec 2026 · SAI Universal Realtors & Developers
NEW Siddharth CO-Operative Housing Society LTD
possession by Dec 2026 · Not Available

Major developers building in Borivali West

Other RERA-registered projects in Mumbai Suburban

Borivli Anjali Chsl
possession by Dec 2027 · Naman Laxmi Developers LLP
Boston Harbor
possession by Sep 2027 · Verdent Infra Bultcon
Bougainvillea
possession by Dec 2026 · Richa Realtors Private Ltd.
Boulevard Tower 4
possession by Jun 2027 · Acme Realties Private Limited
Boulevard Tower 5
possession by Jun 2027 · Acme Realties Private Limited
BPS Aakarshan
declared completion Dec 2022 · Shri R. S. Bhalla & Others

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026