MahaRERA Property Intelligence · Raigarh

CITY ICON

P52000016409 · TALOJA NAVI MUMBAI · promoter City Buildcon

Certificate SignedDue 30 Dec 2022

Delivery & Registration

MahaRERA registrationP52000016409
Registered on10 May 2018
Promoter-declared completion30 Dec 2022
Current statusCertificate Signed
Against todayabout 43 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+16.

BuildingWingsFloorsDeclared completion
CITY ICON1G+1631 Dec 2021

Complaints & Orders

1 complaint is on the MahaRERA record for this project, with orders passed in 1. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC00600000019552505/01/2021Navin Kantilal Thakkar HUF vs M/s City Buildconorder passed

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
30 Dec 202230 Dec 2023The Project has been already completed virtually in Apr-2022 and accordingly application for OC is already filed with CIDCO Ltd on 12-04-2022, but OC is delayed on account of vario

Location, Land & Connectivity

Located at TALOJA NAVI MUMBAI, SECTOR-19 PHASE-II, Panvel, Raigarh, 410208. Per the filed land record, the plot is bounded to the north by PLOT NO 07, to the south by PLOT NO 05, to the east by PLOT NO 04 and to the west by 11 MTR WIDE ROAD. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~23 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park23 km
Bandra Kurla Complex (BKC)27 km
Chhatrapati Shivaji Int'l Airport27 km
Andheri MIDC / SEEPZ27 km
Lower Parel / Worli business district32 km
Nariman Point / Fort35 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Taloja

Ayan Skyway
possession by Sep 2026 · Ibrahim Nazirsha Mukadam
K K Residency
Not filing quarterly progress reports · possession by Sep 2026 · Shree SAI Home Makers
Majestic Planet
possession by Sep 2026 · 365days Construction LLP
Royal Yusra Heights
possession by Sep 2026 · AL-Yusra Developers LLP
Om Unnati
possession by Nov 2026 · Om Group
3anaika
possession by Dec 2026 · Arihant Enterprises

Major developers building in Taloja

Other RERA-registered projects in Raigarh

City Of Music Phase I
possession by Jun 2027 · Nirvana Leisure Realty
City Of Music Phase II
declared completion Jun 2026 · Nirvana Leisure Realty
City Of Music Phase III
possession by Dec 2026 · Nirvana Leisure Realty
City OF Music Phase IV
possession by Dec 2026 · Nirvana Leisure Realty
City Park
possession by Dec 2029 · Nouman Noor Ahmad Patel
City Tower
possession by Aug 2028 · R R Realty

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026