MahaRERA Property Intelligence · Raigarh

CLAN CITY-AQUA MARINE

P52000002531 · TALOJA · promoter Supreme Construction And

Certificate SignedDue 29 Mar 2024

Delivery & Registration

MahaRERA registrationP52000002531
Registered on01 Aug 2017
Promoter-declared completion29 Mar 2024
Current statusCertificate Signed
Against todayabout 28 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Supreme Construction And is the promoter of record on 72 projects, of which 12 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+38.

BuildingWingsFloorsDeclared completion
AQUA MARINE1G+3831 Mar 2022

Complaints & Orders

34 complaints are on the MahaRERA record for this project, with orders passed in 32. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC00600000019769122/07/2021Mr. Vijay Mishrani vs Supreme Construction & Developers Pvt. Ltd.order passed
CC00600000016129818/10/2019RAMESH JOSHI vs SUPREME CONSTRUCTION AND DEVELOPERS PVT LTDorder passed
CC00600000019697717/05/2021Rajshekhar Swami vs Supreme Construction and Developers Private Limitedorder passed
CC00600000019850829/09/2021URMILA THAKUR vs MANULLA MEHBULLAH KANCHWALAorder passed
CC00600000022092401/05/2022URMILA THAKUR vs MANULLA MEHBULLAH KANCHWALAorder passed
CC00600000019923001/12/2021Subhash Chandra Agarwal vs Supreme Construction & Developers Pvt. Ltd.order passed
CC00600000022093322/04/2022Gurcharan Singh Talwar vs Supreme Construction and Developer Pvt Ltdorder passed
CC00600000025177407/07/2022Nanda Maheswari vs M/s. Supreme Construction and Developers Pvt. Ltd.order passed
CC00600000026194218/07/2022Mr. Bhupesh Singh and Mrs. Alka Bhupesh Singh vs M/s. Supreme Constructions and Developersorder passed
CC00600000026194318/07/2022Mrs. Alka Bhupesh Singh and Mr. Bhupesh Singh vs M/s. Supreme Constructions and Developersorder passed
CC00600000033396315/01/2023Chander Parkash vs Supreme construction and developers pvt ltdorder passed
CC00600000033406331/01/2023Nilkanth Arjun Masane vs Supreme Construction and Developers Pvt. Ltd.order passed
CC00600000033414430/01/2023Mrs Shubhada Satish Nene vs Supreme Construction and Developers Pvt Ltdorder passed
CC00600000034418401/02/2023Mr Rajaram Bajirao Bhosale vs Supreme Construction and Developers Pvt Ltdorder passed
CC00600000034426809/02/2023Mrs Smeeta S Lad Mr Amit S Lad Mrs Payal A Lad vs Supreme Construction and Developers Pvt Ltdorder passed
CC00600000035434815/02/2023Jitesh Kumar Chouhan vs Supreme Construction and Developers Pvt Ltdorder passed
CC00600000035434915/02/2023Mrs Seemakurthi Bramara Prasad and Mr Seemakurthi Nagaprasad vs Supreme Construction and Developers Pvt Ltdorder passed
CC00600000035435015/02/2023Shailendra Kumar Mittal and Asha S Mittal vs Supreme Construction and Developers Pvt Ltdorder passed
CC00600000037499528/03/2023Mrs Olive Peter Fernandes and Mr Peter Fernandes vs Supreme Construction and Developers Pvt Ltdorder passed
CC00600000039602001/06/2023Mr Irfan Muniruddin Shaikh vs Supreme Construction and Developers Pvt Ltdorder passed
CC00600000039637021/06/2023Mr Mohammad Abbas Nathani and Mrs Ehnaz M Nathani vs Supreme Construction and Developers Pvt Ltdorder passed
CC00600000039681324/07/2023Shivshankar Ramkedar Dubey vs Supreme Construction and Developers Pvt Ltdorder passed
CC00600000039690101/08/2023Sanjay Mithailal Dubey vs Supreme Construction and Developers Pvt Ltdorder passed
CC00600000047978526/03/2024Dayanand Shantaram Lad vs Supreme Construction and Developers Pvt Ltdorder passed
CC00600000058084609/07/2024Kanchan Sharma vs Supreme Developers & Construction Pvt Ltdorder passed
CC00600000058095027/06/2024Hilary Stevan Rego vs Supreme Construction and Developers Pvt Ltdorder passed
CC1250064724/02/2025ClanCity Welfare association vs Supreme Construction and Developers Private Limitedorder passed
CC1260013909/01/2026Sanket Omprakash Jhaver vs Supreme Construction and Developers Private Limitedorder passed
CC1250160515/05/2025Mohd Ayub Mohd Hanif Qureshi vs Supreme Construction and Developers Private Limitedorder passed
CC1250346028/09/2025Manju Ashok Kharwad vs Supreme Construction and Developers Private Limitedorder passed
CC1250391007/11/2025Deepak Nambiar vs Supreme Construction and Developers Private Limitedorder passed
CC1250423029/11/2025Rajiv Mendiratta vs Supreme Construction and Developers Private Limitedorder passed
CC1260038020/01/2026Dilip Agrawal vs Supreme Construction and Developers Private Limitedpending / no order on file
CC1260052730/01/2026Shrikant Mane vs Supreme Construction and Developers Private Limitedpending / no order on file

Legal & Litigation

The promoter has declared 4 court cases on this project to MahaRERA. 1 is still pending. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your flat. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Bombay High Court340,348,342,343,351,344,3492017Final Order Passed Matter Disposed
Bombay High Court77,79,84,80,75,74,762017Final Order Passed Matter Disposed
Bombay High Court191,192,193,194,195,310,3112017Final Order Passed Matter Disposed
Bombay High Court202742017Pending

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
29 Mar 202429 Mar 2024This project has a special status as it is in collaboration with regional planning authority, MMRDA, constituted by the state Government. As per the role defined in the scheme, the

Location, Land & Connectivity

Located at TALOJA, NH4, Mumbai City, Mumbai City, 410208. Per the filed land record, the plot is bounded to the north by Survey No 58, to the south by Tower No 8 Emerald, to the east by Open Sapce and to the west by Open Space. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~19 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park19 km
Bandra Kurla Complex (BKC)22 km
Chhatrapati Shivaji Int'l Airport22 km
Andheri MIDC / SEEPZ22 km
Lower Parel / Worli business district28 km
Nariman Point / Fort32 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Supreme Construction And Developers Private Limited is the promoter on 9 MahaRERA-registered projects, of which 9 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

See every Supreme Construction And Developers Private L project & its RERA track record →

Other flagged projects by Supreme Construction And Developers Private L

Supreme Construction And Developers Private Limited
Past its declared completion dateRaigarh
Supreme Construction And Developers Private Limited
Past its declared completion dateRaigarh
Supreme Construction And Developers Private Limited
Past its declared completion dateRaigarh
Supreme Construction And Developers Private Limited
Past its declared completion dateRaigarh
Supreme Construction And Developers Private Limited
Past its declared completion dateRaigarh
Supreme Construction And Developers Private Limited
Past its declared completion dateRaigarh

Other RERA-registered projects in Taloja

Ayan Skyway
possession by Sep 2026 · Ibrahim Nazirsha Mukadam
K K Residency
Not filing quarterly progress reports · possession by Sep 2026 · Shree SAI Home Makers
Majestic Planet
possession by Sep 2026 · 365days Construction LLP
Royal Yusra Heights
possession by Sep 2026 · AL-Yusra Developers LLP
Om Unnati
possession by Nov 2026 · Om Group
3anaika
possession by Dec 2026 · Arihant Enterprises

Major developers building in Taloja

Other RERA-registered projects in Raigarh

Clan City-Diamond
declared completion Mar 2024 · Supreme Construction And Developers Priv
Clan City-Emerald
declared completion Mar 2024 · Supreme Construction And Developers Priv
Clan City-Garnet
declared completion Mar 2024 · Supreme Construction And Developers Priv
Clan City-Pearl
declared completion Mar 2024 · Supreme Construction And Developers Priv
Clan City-Ruby
declared completion Mar 2024 · Supreme Construction And Developers Priv
Clan City - Sapphire
declared completion Mar 2024 · Supreme Construction And Developers Priv

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026