Mumbai/Project record

MahaRERA · the public record

CLAN CITY-GARNET

TALOJA · Supreme Construction and Developers Private Limited

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

29 Mar 2024declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

29 Mar 2024

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52000002335

Delivery and registration

When is the project declared for completion?

CLAN CITY-GARNET is registered with MahaRERA as P52000002335 and the promoter has declared completion for 29 Mar 2024.

29 Mar 2024

declared completion

30months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52000002335
Registered on31 Jul 2017
Promoter-declared completion29 Mar 2024
Current statusCertificate Signed
Against todayabout 30 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for CLAN CITY-GARNET record 27 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 27 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Supreme Construction is the promoter of record on 73 projects registered with MahaRERA, 12 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

73projects

registered with MahaRERA

12flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for CLAN CITY-GARNET in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+38.

BuildingWingsFloorsDeclared completion
GARNET1G+3831 Mar 2022

Legal and disputes

What disputes are disclosed?

38 complaints are on the MahaRERA record for CLAN CITY-GARNET, with orders passed in 38 of them.

38complaints

38with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000017147410/11/2019NIKHIL NAMDEO PATIL vs SUPREME CONSTRUCTION AND DEVELOPERS PVT. LTD.order passed
CC00600000005812016/02/2019HERAMB KSHIRSAGAR vs Supreme Construction and Developers Pvt. Ltd.order passed
CC00600000024129931/05/2022Heramb Kshirsagar vs Supreme Construction and Developers Pvt. Ltd.order passed
CC00600000019662706/05/2021NARAYAN SWAMI RAMESH vs M/S SUPREME CONSTRUCTION AND DEVELOPERS PVT, LTD.order passed
CC00600000033398617/01/2023Mrs Vandana Jiwat Manglani vs Supreme Construction and Developers Pvt Ltdorder passed
CC00600000033406021/01/2023Sunil Kumar Sahu vs Supreme Construction and Developers Pvt Ltdorder passed
CC00600000033412827/01/2023Mrs Seema Dattatray Gadhave vs Supreme Construction and Developers Pvt Ltdorder passed
CC00600000035437116/02/2023Yashwant Kalulal Jain vs Supreme Construction and Developers Pvt Ltdorder passed
CC00600000036476721/03/2023ARUN NIVRUTI SHIRSEKAR vs SupremeConstruction & Developers Pvt Ltd.order passed
CC00600000037478314/03/2023Kundan Chandrakant Bhagat vs Supreme Construction and Developers Pvt Ltdorder passed
CC00600000037479315/03/2023Murarilal Bimriwala vs Supreme Construction and Developers Pvt Ltdorder passed
CC00600000037488922/03/2023Lancy James Nazareth vs Supreme Construction and Developers Pvt Ltdorder passed
CC00600000037516006/04/2023Rishi Kumar Sharma vs Supreme Construction and Developers Pvt Ltdorder passed
CC00600000037536923/04/2023Satish Madhav Rajput vs Supreme Construction and Developers Pvt Ltdorder passed
CC00600000039583316/05/2023Prashant Bhure vs Supreme Construction and Developers Pvt Ltdorder passed
CC00600000039587520/05/2023Mrs Munni Kumari and Mr Tarun Kumar vs Supreme Construction and Developers Pvt Ltdorder passed
CC00600000039614409/06/2023Surendra Manjappa Poojari vs Supreme Construction and Developers Pvt Ltdorder passed
CC00600000039670821/07/2023RAHUL RAMESH BHALLA vs Supreme Construction and Developers Private Limitedorder passed
CC00600000039653618/07/2023MR ARVIND BAPURAO THOMBRE vs M/S SUPREME CONSTRUCTION AND DEVELOPERS PVT LTDorder passed
CC00600000040810812/11/2023Yaseen Dawood Bangi vs SUPREME CONSTRUCTION AND DEVELOPERS PRIVATED LTDorder passed
CC00600000040814212/11/2023Hafiza Yakub Chilwan vs SUPREME CONSTRUCTION AND DEVELOPERS PRIVATE LTDorder passed
CC00600000047980127/03/2024Islauddin Shantaram Hussain vs Supreme Construction and Developers Private Limitedorder passed
CC00600000058083609/07/2024Kanchan Sharma vs SUPREME DEVELOPERS & CONSTRUCTION PVT LTDorder passed
CC1240036607/10/2024Shuchita Sanjay Multani vs Supreme Construction and Developers Private Limitedorder passed
CC1250026725/01/2025lokesh jagdish kasera vs -order passed
CC1250026925/01/2025lokesh jagdish kasera vs -order passed
CC1250039005/02/2025lokesh jagdish kasera vs -order passed
CC1250039105/02/2025lokesh jagdish kasera vs -order passed
CC1250041207/02/2025lokesh jagdish kasera vs -order passed
CC1250042810/02/2025lokesh jagdish kasera vs -order passed
CC1250064924/02/2025ClanCity Welfare association vs Supreme Construction and Developers Private Limitedorder passed
CC1250311104/09/2025Onkar Singh Plaha vs Supreme Construction and Developers Private Limitedorder passed
CC1250403415/11/2025Baburao Gyanoba Paulkar vs Supreme Construction and Developers Private Limitedorder passed
CC1250311204/09/2025Onkar Singh Plaha vs Supreme Construction and Developers Private Limitedorder passed
CC1250382701/11/2025Anil Patil vs Supreme Construction and Developers Private Limitedorder passed
CC1260003203/01/2026Meenakshi Bhanushali vs Supreme Construction and Developers Private Limitedorder passed
CC1260023713/01/2026Usha Sadanand Shetty vs Supreme Construction and Developers Private Limitedorder passed
CC1260026915/01/2026Pankaj Shukla vs Supreme Construction and Developers Private Limitedorder passed

Legal & Litigation

The promoter has declared 4 court cases on this project to MahaRERA. 1 is still pending. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your home. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Bombay High Court340,348,342,343,351,344,3492017Final Order Passed Matter Disposed
Bombay High Court77,79,84,80,75,74,762017Final Order Passed Matter Disposed
Bombay High Court191,192,193,194,195,310,3112017Final Order Passed Matter Disposed
Bombay High Court202742017Pending

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered29 Mar 2024This project has a special status as it is in collaboration with regional planning authority, MMRDA, constituted by the state Government. As per the role defined in the scheme, the

Location, Land & Connectivity

Located at TALOJA, NH4, Mumbai City, Mumbai City, 410208. Per the filed land record, the plot is bounded to the north by Survey No 58, to the south by Open Space and RG-S-POND, to the east by Tower No 6 Topaz and to the west by Tower No 8 Emerald. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~19 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park19 km
Bandra Kurla Complex (BKC)22 km
Chhatrapati Shivaji Int'l Airport22 km
Andheri MIDC / SEEPZ23 km
Lower Parel / Worli business district28 km
Nariman Point / Fort32 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Supreme Construction And Developers Private Limited is the promoter on 9 MahaRERA-registered projects, of which 9 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

See every Supreme Construction And Developers Private L project & its RERA track record →

Other flagged projects by Supreme Construction And Developers Private L

Supreme Construction And Developers Private Limited
Past its declared completion dateRaigarh
Supreme Construction And Developers Private Limited
Past its declared completion dateRaigarh
Supreme Construction And Developers Private Limited
Past its declared completion dateRaigarh
Supreme Construction And Developers Private Limited
Past its declared completion dateRaigarh
Supreme Construction And Developers Private Limited
Past its declared completion dateRaigarh
Supreme Construction And Developers Private Limited
Past its declared completion dateRaigarh

Other RERA-registered projects in Taloja

Ayan Skyway
possession by Sep 2026 · Ibrahim Nazirsha Mukadam
K K Residency
Not filing quarterly progress reports · possession by Sep 2026 · Shree SAI Home Makers
Majestic Planet
possession by Sep 2026 · 365days Construction LLP
Royal Yusra Heights
possession by Sep 2026 · AL-Yusra Developers LLP
Om Unnati
possession by Nov 2026 · Om Group
Arihant Amisha Phase II
possession by Dec 2026 · Arihant Aashiyana Private Limited

Other RERA-registered projects in Raigarh

Clan City-Pearl
declared completion Mar 2024 · Supreme Construction And Developers Priv
Clan City-Ruby
declared completion Mar 2024 · Supreme Construction And Developers Priv
Clan City - Sapphire
declared completion Mar 2024 · Supreme Construction And Developers Priv
Clan City-Topaz
declared completion Mar 2024 · Supreme Construction And Developers Priv
Clan City-Turquoise
declared completion Mar 2024 · Supreme Construction And Developers Priv
Classic Commercial Services
declared completion Dec 2021 · Classic Commercial Services Private Limi

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026