CLAN CITY-TURQUOISE

TALOJA · Supreme Construction and Developers Private Limited

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

29 Mar 2024declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

29 Mar 2024

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52000004376

Delivery and registration

When is the project declared for completion?

CLAN CITY-TURQUOISE is registered with MahaRERA as P52000004376 and the promoter has declared completion for 29 Mar 2024.

29 Mar 2024

declared completion

30months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52000004376
Registered on09 Aug 2017
Promoter-declared completion29 Mar 2024
Current statusCertificate Signed
Against todayabout 30 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for CLAN CITY-TURQUOISE record 27 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 27 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Supreme Construction is the promoter of record on 73 projects registered with MahaRERA, 12 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

73projects

registered with MahaRERA

12flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for CLAN CITY-TURQUOISE in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+38.

BuildingWingsFloorsDeclared completion
TURQUOISE1G+3831 Mar 2022

Legal and disputes

What disputes are disclosed?

20 complaints are on the MahaRERA record for CLAN CITY-TURQUOISE, with orders passed in 19 of them.

20complaints

19with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000017147610/11/2019NIKHIL NAMDEO PATIL vs SUPREME CONSTRUCTION AND DEVELOPERS PVT. LTD.order passed
CC00600000034419802/02/2023Mr Madan Singh Bhandari vs Supreme Construction and Developers Pvt Ltdorder passed
CC00600000035447022/02/2023Madhuri Kamlesh Dubey and Kamlesh R Dubey vs Supreme Construction and Developers Pvt Ltdorder passed
CC00600000036459102/03/2023Akhilesh Raj Parashar vs Supreme Construction and Developers Pvt Ltdorder passed
CC00600000037481917/03/2023MR VISHWANATH R SINGH AND MRS INDU V SINGH vs M/S SUPREME CONSTRUCTION AND DEVELOPERS PVT LTDorder passed
CC00600000037509503/04/2023Mr Kuldeep Kumar Sharma and Mrs Shikha Sharma vs Supreme Construction and Developers Pvt Ltdorder passed
CC00600000039588622/05/2023Nirmala Mustafa Momin vs M/s Supreme Construction and Developers Lvt Ltdorder passed
CC00600000039604502/06/2023Rohan Mahendra Sheth and Rekha Rohan Sheth vs Supreme Construction and Developers Pvt Ltdorder passed
CC00600000039621914/06/2023Syed Masood Ahmed vs Supreme Construction and Developers Pvt Ltdorder passed
CC00600000039682725/07/2023Palak Mukesh Rathod vs Supreme Construction and developer Pvt Limitedorder passed
CC00600000040811208/11/2023Yashodha Prakash Pillai vs Supreme Construction and Developers Pvt Ltdorder passed
CC00600000058084809/07/2024Kanchan Sharma vs Supreme Developers & Construction Pvt Ltdorder passed
CC1250036002/02/2025RANBIR SINGH PAPINDER SINGH GODHAN vs Supreme Construction and Developers Private Limitedorder passed
CC1250062922/02/2025ClanCity Welfare association vs Supreme Construction and Developers Private Limitedorder passed
CC1250434408/12/2025Rochelle Adil Baig vs Supreme Construction and Developers Private Limitedorder passed
CC1250400613/11/2025Maulik Shailesh Mehta vs Supreme Construction and Developers Private Limitedorder passed
CC1250419527/11/2025Pankaj Patil vs Supreme Construction and Developers Private Limitedorder passed
CC1250428904/12/2025Meena Vishnu Ramane vs Supreme Construction and Developers Private Limitedorder passed
CC1250470430/12/2025Nisar Shahab vs Supreme Construction and Developers Private Limitedorder passed
CC1260051129/01/2026Rishi Dusija vs Supreme Construction and Developers Private Limitedpending / no order on file

Legal & Litigation

The promoter has declared 4 court cases on this project to MahaRERA. 1 is still pending. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your home. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Bombay High Court340,348,342,343,351,344,3492017Final Order Passed Matter Disposed
Bombay High Court77,79,84,80,75,74,762017Final Order Passed Matter Disposed
Bombay High Court191,192,193,194,195,310,3112017Final Order Passed Matter Disposed
Bombay High Court202742017Pending

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered29 Mar 2024This project has a special status as it is in collaboration with regional planning authority, MMRDA, constituted by the state Government. As per the role defined in the scheme, the

Location, Land & Connectivity

Located at TALOJA, NH4, Mumbai City, Mumbai City, 410208. Per the filed land record, the plot is bounded to the north by OLD NH-4, to the south by RG-S-POND, to the east by Tower No 1 Sapphire and to the west by Tower No 3 Diamond. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~19 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park19 km
Bandra Kurla Complex (BKC)22 km
Chhatrapati Shivaji Int'l Airport23 km
Andheri MIDC / SEEPZ23 km
Lower Parel / Worli business district28 km
Nariman Point / Fort32 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Supreme Construction And Developers Private Limited is the promoter on 9 MahaRERA-registered projects, of which 9 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

See every Supreme Construction And Developers Private L project & its RERA track record →

Other flagged projects by Supreme Construction And Developers Private L

Supreme Construction And Developers Private Limited
Past its declared completion dateRaigarh
Supreme Construction And Developers Private Limited
Past its declared completion dateRaigarh
Supreme Construction And Developers Private Limited
Past its declared completion dateRaigarh
Supreme Construction And Developers Private Limited
Past its declared completion dateRaigarh
Supreme Construction And Developers Private Limited
Past its declared completion dateRaigarh
Supreme Construction And Developers Private Limited
Past its declared completion dateRaigarh

Other RERA-registered projects in Taloja

Ayan Skyway
possession by Sep 2026 · Ibrahim Nazirsha Mukadam
K K Residency
Not filing quarterly progress reports · possession by Sep 2026 · Shree SAI Home Makers
Majestic Planet
possession by Sep 2026 · 365days Construction LLP
Royal Yusra Heights
possession by Sep 2026 · AL-Yusra Developers LLP
Om Unnati
possession by Nov 2026 · Om Group
Arihant Amisha Phase II
possession by Dec 2026 · Arihant Aashiyana Private Limited

Other RERA-registered projects in Raigarh

Classic Commercial Services
declared completion Dec 2021 · Classic Commercial Services Private Limi
Classic Pride
declared completion Feb 2026 · Shiv Classic Enterprises
Cloud 21
possession by Sep 2028 · Kricon Livspaces LLP
Cloud 9
declared completion Dec 2025 · Neelkanth Enterprises
Cloud Castle
declared completion Aug 2026 · JKS Homes
Cluster A
possession by Dec 2026 · Shibam Associates

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.