Construction of Bldg no.22 B at Kopari powai

Mumbai Suburban · MHADA

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Jun 2019declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Jun 2019

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800000046

Delivery and registration

When is the project declared for completion?

Construction of Bldg no.22 B at Kopari powai is registered with MahaRERA as P51800000046 and the promoter has declared completion for 30 Jun 2019.

30 Jun 2019

declared completion

87months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800000046
Registered on16 Jun 2017
Promoter-declared completion30 Jun 2019
Current statusCertificate Signed
Against todayabout 87 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Construction of Bldg no.22 B at Kopari powai record 9 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 9 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Mhada is the promoter of record on 49 projects registered with MahaRERA, 2 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

49projects

registered with MahaRERA

2flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Construction of Bldg no.22 B at Kopari powai in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+15.

BuildingWingsFloorsDeclared completion
22 B Powai1G+15-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered30 Jun 2019Previously the MCGM has not issued the Occupation Certificate for the said Bldg. from 9th floor up to 14th floor. Now the MHADA is declared as Special Planning Authority, request

Location, Land & Connectivity

Located at Adi Shankaracharya Marg, Andheri, Mumbai Suburban, 400076. Per the filed land record, the plot is bounded to the north by Forbes Land , to the south by bldg no 22 A, to the east by Hill area and to the west by RG 18 . These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~1 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Powai / Hiranandani business park1 km
Andheri MIDC / SEEPZ4 km
Chhatrapati Shivaji Int'l Airport6 km
Bandra Kurla Complex (BKC)8 km
Lower Parel / Worli business district16 km
Nariman Point / Fort24 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Mhada is the promoter on 18 MahaRERA-registered projects, of which 2 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

See every Mhada project & its RERA track record →

Other flagged projects by Mhada

Mhada
Past its declared completion dateMumbai Suburban

Other RERA-registered projects in Powai

Kanakia Future City E
possession by Sep 2026 · Kanakia Future Realty Private Limited
Mars- Suncity Housing Phase II
possession by Dec 2026 · Suncity Housing
Prathamesh Galaxy
Registration suspended · possession by Dec 2026 · Saileedevelopers
Gurukrupa Gyanam
possession by Dec 2026 · Gurukrupa Realcon Infrabuild LLP
Highland A B C D AND E Wing
possession by Dec 2026 · HGP Community Pvt. Ltd.
Kanakia Silicon Valley F
possession by Dec 2026 · Kanakia Future Realty Private Limited

Major developers building in Powai

Other RERA-registered projects in Mumbai Suburban

Construction Of Building No 04 Consisting Of Single Wing Comprising Of Stilt 5P 33 Floors 128 Ts
possession by Oct 2028 · Mumbai Housing And Area Development Boar
Construction Of LIG And MIG Tenement At Virar Bolinj
declared completion Mar 2018 · Konkan Housing AND Area Development Boar
Constrution Of 24 LIG Ts On CTS No 356 P At Siddharth Nagar Goregaon West Mumbai 400062
declared completion Jun 2019 · Mumbai Housing AND Area Development Boar
Contendre Enclave
declared completion May 2026 · Contendre Infratech Pvt. Ltd.
Continuum
declared completion Dec 2019 · Narang & Ruchi Developers
Conwood Housing-Palace Royale
declared completion Sep 2020 · Conwood Housing Private Limited

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026