MahaRERA Property Intelligence · Mumbai Suburban

MIG / LIG Ts CTS No 165 at Tagore Nagar, Vikhroli, E

P51800000100 · promoter Mhada

Certificate SignedDue 30 Jun 2019

Delivery & Registration

MahaRERA registrationP51800000100
Registered on02 Jul 2017
Promoter-declared completion30 Jun 2019
Current statusCertificate Signed
Against todayabout 85 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Mhada is the promoter of record on 49 projects, of which 2 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8.

BuildingWingsFloorsDeclared completion
Sarvodaya bldg1G+8-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
30 Jun 201930 Jun 2019Now the MHADA is declared as Special Planning Authority, the request for releasing O.C. for the same is made.

Location, Land & Connectivity

Located at Andheri, Mumbai Suburban, 400079. Per the filed land record, the plot is bounded to the north by GARDEN, to the south by CHAWL NO 286, to the east by D P ROAD and to the west by CHAWL NO 271. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~3 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Powai / Hiranandani business park3 km
Chhatrapati Shivaji Int'l Airport6 km
Andheri MIDC / SEEPZ7 km
Bandra Kurla Complex (BKC)7 km
Lower Parel / Worli business district15 km
Nariman Point / Fort22 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Mhada is the promoter on 18 MahaRERA-registered projects, of which 2 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

See every Mhada project & its RERA track record →

Other flagged projects by Mhada

Mhada
Past its declared completion dateMumbai Suburban

Other RERA-registered projects in Vikhroli

Vasundhara
possession by Sep 2026 · Yogesh Shantilal Thakkar
THE X Ghatkopar
possession by Dec 2026 · Arihant Realtors
Manthan Acropolis
possession by Dec 2026 · Manthan Development Corporation
Omtech VKW Business Tower
possession by Mar 2027 · Omtech Enterprises
Aikya Roots
possession by Jun 2027 · Racek Industries PVT LTD
Metro Crown
possession by Dec 2027 · Metro Enterprises

Major developers building in Vikhroli

Other RERA-registered projects in Mumbai Suburban

Milan Aura
possession by Dec 2027 · Milan Interbuilt Private Limited
Milan Bliss
declared completion Aug 2025 · Milan Interbuilt Private Limited
Milan Mandir NX
possession by Mar 2027 · Milan Life Spaces LLP
Milan Milap CO OP Housing Society LTD
possession by Dec 2026 · Milan Milap CO OP Housing Society Limite
Milan Residency
declared completion Dec 2020 · M/s Milan Builders
Milap CO-Operative Housing Society
declared completion Mar 2018 · Golden Eyecon

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026