MahaRERA Property Intelligence · Mumbai Suburban

CONTENDRE ENCLAVE

P51800053218 · PLOT NO 9C · promoter Contendre Infratech Pvt

Certificate SignedDue 31 May 2026

Delivery & Registration

MahaRERA registrationP51800053218
Registered on23 Oct 2023
Promoter-declared completion31 May 2026
Current statusCertificate Signed
Against todayabout 2 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Contendre Infratech Pvt is the promoter of record on 3 projects, of which none currently carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Construction Progress

MahaRERA's cost filing puts construction at ~84.2% of the estimated project cost incurred as of the last certificate (₹17.52 Cr spent against a ₹20.81 Cr estimate). This financial % is the regulator's own proxy for how much is physically built — the closest public read on real progress, and one a brochure never shows. The declared completion date has already passed while the cost-incurred filing sits at ~84.2% — a wide gap between the promise and the money actually spent on site.

Cost-incurred % as last certified to MahaRERA; it can lag on-site reality between filings. Confirm the current stage and the latest Form 2 before you book.

Sales & Inventory

Of 14 homes filed with MahaRERA, 5 are sold/booked and 9 remain available (~36% sold) — early in sales — more choice of units now, but confirm the developer has the pre-sales to fund the build. Buyers have committed ₹4.26 Cr in agreement value so far. Of that, ₹2.22 Cr (~52%) is already collected, ₹2.04 Cr receivable — a read on how far along these sales really are. Note: the project registers 30 homes in total, but this sold/unsold inventory filing covers only 14 of them — the other 16 aren't in the ledger yet. Ask the builder what they are (an unreleased phase, held-back stock, or non-saleable/car-park units) before reading too much into the percentage. This is the promoter's own reported inventory as at the last compliance filing; confirm current availability directly.

What buyers actually paid: across 5 registered agreements, the effective carpet rate is ₹12,360/sqft (typical range ₹12,355–₹12,415) — computed from the agreement values and carpet areas the promoter filed, not broker quotes. Compare your quote against this before negotiating.

The unsold units on the filing — if you're quoted a unit NOT on this list, ask why it shows as sold/booked on the RERA record:

FloorUnitCarpetReckoner value
Floor 1102677 sqft (62.86 sqm)₹83.63 Lakh
Floor 111103726 sqft (67.42 sqm)₹89.59 Lakh
Floor 2201677 sqft (62.94 sqm)₹83.74 Lakh
Floor 3301677 sqft (62.94 sqm)₹83.74 Lakh
Floor 4403588 sqft (54.67 sqm)₹72.91 Lakh
Floor 5503677 sqft (62.85 sqm)₹83.54 Lakh
Floor 6603677 sqft (62.85 sqm)₹83.54 Lakh
Floor 7703890 sqft (82.66 sqm)₹1.10 Cr
Floor 9902911 sqft (84.66 sqm)₹1.13 Cr

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing — still confirm your specific unit's status in the agreement.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+12 and 30 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
CONTENDRE ENCLAVE1G+1230-

Unit mix on the filing: 30 residential.

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at PLOT NO 9C, NA , Mumbai City, Mumbai City, 400080. Per the filed land record, the plot is bounded to the north by CTS NO 551-54, to the south by BY TRIMURTHY MARG, to the east by CTS NO 551-66 and to the west by CTS NO 551-67. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~34 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park34 km
Andheri MIDC / SEEPZ37 km
Chhatrapati Shivaji Int'l Airport39 km
Bandra Kurla Complex (BKC)40 km
Lower Parel / Worli business district48 km
Nariman Point / Fort53 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Contendre Infratech Pvt. Ltd. is the promoter on 3 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by Contendre Infratech Pvt. Ltd.

Contendre Infratech Pvt. Ltd.
FlaggedMumbai Suburban
Contendre Infratech Pvt. Ltd.
FlaggedRaigarh

Other RERA-registered projects in Mulund West

Kailash Residency
possession by Aug 2026 · Tridev Shreeji Associates
Ananta
possession by Aug 2026 · K Ajmera Developers
AAI Satidevi Paradise
possession by Sep 2026 · Shreenath Developers
Laizer Elegance
Not filing quarterly progress reports · possession by Sep 2026 · Laizer Builders & Developers
THE NEW Anand Deep CHS LTD
possession by Sep 2026 · Shreejee Buildcon
Tirupati Apartments Chsl
possession by Oct 2026 · Tirupati Aparmtnets CO Operative Housing

Major developers building in Mulund West

Other RERA-registered projects in Mumbai Suburban

Contendre Heights
declared completion Nov 2023 · Contendre Infratech Pvt. Ltd.
Continuum
declared completion Dec 2019 · Narang & Ruchi Developers
Conwood Astoria Tower A
declared completion Dec 2019 · Conwood Realty Private Limited
Conwood Housing-Palace Royale
declared completion Sep 2020 · Conwood Housing Private Limited
Conwood Paragon
possession by Dec 2027 · Consolidated Crop Protection Private Lim
Corinthia -Tower 1 And Tower 2
possession by May 2031 · Lodha Developers Limited

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026