Cosmos Horizon

Thane · Concorde Developers

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Dec 2018declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2018

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51700005092

Delivery and registration

When is the project declared for completion?

Cosmos Horizon is registered with MahaRERA as P51700005092 and the promoter has declared completion for 31 Dec 2018.

31 Dec 2018

declared completion

93months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51700005092
Registered on09 Aug 2017
Promoter-declared completion31 Dec 2018
Current statusCertificate Signed
Against todayabout 93 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Cosmos Horizon record 6 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 6 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Concorde is the promoter of record on 8 projects registered with MahaRERA, none of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

8projects

registered with MahaRERA

0flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Cosmos Horizon in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+19.

BuildingWingsFloorsDeclared completion
Cosmos horizon Building no 4 Skyline 12th to 27th floor1G+1931 Dec 2018

Legal and disputes

What disputes are disclosed?

1 complaint is on the MahaRERA record for Cosmos Horizon, with orders passed in 0 of them.

1complaint

0with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC1240098303/12/2024Girish G Kedar vs Concorde Developerspending / no order on file

Legal & Litigation

The promoter has declared 1 court case on this project to MahaRERA. 1 is still pending. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your home. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Supreme Court Of India318482013Pending

Location, Land & Connectivity

Located at Thane, Thane, Thane, 400606. Per the filed land record, the plot is bounded to the north by 40 mtr wide D P Road S No 194 3B 193 2B, to the south by S No 192 2A 1, to the east by S no 180 and to the west by S no 192 3A. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~13 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Powai / Hiranandani business park13 km
Andheri MIDC / SEEPZ14 km
Chhatrapati Shivaji Int'l Airport18 km
Bandra Kurla Complex (BKC)20 km
Lower Parel / Worli business district28 km
Nariman Point / Fort36 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Concorde Developers is the promoter on 2 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

See every Concorde Developers project & its RERA track record →

Other RERA-registered projects in Thane

Shreesandesh Heights
possession by Sep 2026 · Aditya Enterprises
Elito Grand Central
possession by Dec 2026 · Fortune Infracreators Private Limited
Glorio Grand Central
possession by Dec 2026 · Ekdant Constructions And Developers Priv
Stella Grand Central
possession by Dec 2026 · Fortune Infracreators Private Limited
Jai Bhavani Chs Ltd SRA Project
possession by Dec 2026 · Heer Realty Ventures PVT LTD
The Address By GS Tower A
possession by Dec 2026 · Raymond Limited

Other RERA-registered projects in Thane

Cosmos Jewels
declared completion Mar 2018 · Cosmos Lifestyle
Courtyard - Asteria A
possession by Dec 2027 · Courtyard Real Estate Private Limited
Courtyard - Asteria B
possession by Dec 2027 · Courtyard Real Estate Private Limited
Courtyard - Asteria C
possession by Dec 2027 · Courtyard Real Estate Private Limited
Courtyard - Florence
declared completion Dec 2021 · Courtyard Real Estate Private Limited
Courtyard - Ivy
declared completion Dec 2021 · Courtyard Real Estate Private Limited

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026