Mumbai/Project record

MahaRERA · the public record

D N Nagar Dwarka CHS Ltd.

Andheri West · SSSC Escatics Pvt. Ltd.

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Mar 2021declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Mar 2021

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800003897

Delivery and registration

When is the project declared for completion?

D N Nagar Dwarka CHS Ltd. is registered with MahaRERA as P51800003897 and the promoter has declared completion for 31 Mar 2021.

31 Mar 2021

declared completion

66months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800003897
Registered on06 Aug 2017
Promoter-declared completion31 Mar 2021
Current statusCertificate Signed
Against todayabout 66 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for D N Nagar Dwarka CHS Ltd. record 15 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 15 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Sssc Escatics is the promoter of record on 5 projects registered with MahaRERA, 3 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

5projects

registered with MahaRERA

3flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for D N Nagar Dwarka CHS Ltd. in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+14.

BuildingWingsFloorsDeclared completion
Sai Dwarka1G+1431 Dec 2018

Legal and disputes

What disputes are disclosed?

14 complaints are on the MahaRERA record for D N Nagar Dwarka CHS Ltd., with orders passed in 12 of them.

14complaints

12with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000005538421/07/2018MAHESH HOTCHAND THAWANI vs SSSC ESCATICS PRIVATE LIMITEDorder passed
CC00600000005541021/07/2018RINKU MAHESH THAWANI vs SSSC ESCATICS PRIVATE LIMITEDorder passed
CC00600000025138530/07/2022Mr. Kuldeep Singh Sarin vs M/s SSSC Escatics Pvt. Ltd.order passed
CC00600000026201322/07/2022PUJA ISHWAR vs SSSC ESCATICS PVT LTDorder passed
CC00600000029279027/09/2022Ritesh Chudasama vs M/s. SSSC ESCATICS Pvt. Ltd.order passed
CC00600000030299218/10/2022Jaikumar Prakash Soni vs M/s. SSSC ESCATICS Pvt. Ltd.order passed
CC00600000030316001/11/2022Suraj Bhaskar Baadkar vs M/s. SSSC ESCATICS Pvt Ltdorder passed
CC00600000030316604/11/2022Prachi Pradeep Maroo vs SSSC Escatics Private Limitedorder passed
CC00600000037524612/04/2023Neetu Arjun Sharma vs M/s SSSC ESCATICS Pvt Ltdorder passed
CC00600000039809707/01/2024Vijay Jadhav vs Director of the SSSC Escatics Private Limitedorder passed
CC00600000048008917/04/2024SUNITA DARSHANLAL OBEROI vs Shree Sai Sagar Consultantsorder passed
CC00600000050052321/05/2024Rajkumar Singh vs SSSC Escatics Pvt. Ltd.order passed
CC1250031629/01/2025Vimmi Amar Singh vs SSSC Escatics Pvt. Ltd.pending / no order on file
CC1260038621/01/2026Parthiv Vinaykant Parekh vs SSSC Escatics Pvt. Ltd.pending / no order on file

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 2 times, as recorded on the register.

FromExtended toStated reason
as registered31 Dec 2019I Mr. Jayesh Tanna, promoter of the project D N Nagar Dwarka CHS Ltd a society redevelopment project at plot having Survey No. 106A, CTS no 195 part at D N Nagar, Andheri, Mumbai S
31 Dec 201931 Mar 2021We request for a further extension of 15 months as there was an unintentional delay in completing the project due to certain mitigating circumstances. These mitigating circumstance

Location, Land & Connectivity

Located at Andheri West, D N Nagar Ganesh Chawk, Borivali, Mumbai Suburban, 400053. Per the filed land record, the plot is bounded to the north by Building no 27, to the south by Building no 29, to the east by Bhavans college and to the west by 40 ft wide road. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~4 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Andheri MIDC / SEEPZ4 km
Chhatrapati Shivaji Int'l Airport5 km
Bandra Kurla Complex (BKC)7 km
Powai / Hiranandani business park8 km
Lower Parel / Worli business district14 km
Nariman Point / Fort22 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Sssc Escatics Pvt. Ltd. is the promoter on 3 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other RERA-registered projects in Andheri West

Royale
possession by Sep 2026 · Khoker Synergy Developers
Transcon Triumph Tower 3
possession by Sep 2026 · Transcon Triumph Phase 2 Private Limited
ARC ONE
possession by Dec 2026 · Chandra Gupta Estates Private Limited
MDM Maestro
possession by Dec 2026 · MDM Realty LLP
Platinum Grandeur
possession by Dec 2026 · Platinum Strategic Developers LLP
Vengurlekars Chaitra
possession by Dec 2026 · Vengurlekars Shreesai Builders And Devel

Major developers building in Andheri West

Other RERA-registered projects in Mumbai Suburban

D N Nagar Jai Bhavani CHS Ltd
declared completion Dec 2021 · Sai Siddhant Developers
D N Nagar Krishna CHS Ltd
declared completion Dec 2023 · Sai Siddhant Developers
D N Nagar Shivneri CHS Ltd
declared completion Mar 2023 · Sai Siddhant Developers
D N Nagar Suryakiran CHS Limited
declared completion Dec 2021 · Sai Siddhant Developers
D Solitaire
declared completion Jun 2026 · Krishnan AND Kamal Associates
Dadamiyas Deluxe Apartment
declared completion Mar 2023 · Dadamiya Infrastructure & Deluxe Inf

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026