Mumbai/Project record

MahaRERA · the public record

EMBASSY CITADEL

LOWER PAREL · EQUINOX INDIA INFRAESTATE LIMITED

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

261units filed as unsoldInventory · 20 September 2026
30 Jun 2034declared completionMahaRERA registration · read 12 Jul 2026
158registered unitsMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Jun 2034

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · PR1170002501931

Delivery and registration

When is the project declared for completion?

EMBASSY CITADEL is registered with MahaRERA as PR1170002501931 and the promoter has declared completion for 30 Jun 2034.

30 Jun 2034

declared completion

93months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationPR1170002501931
Registered on29 Dec 2025
Promoter-declared completion30 Jun 2034
Current statusCertificate Signed
Against today93 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for EMBASSY CITADEL record 2 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 2 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Equinox India Infraestate is the promoter of record on 8 projects registered with MahaRERA, none of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

8projects

registered with MahaRERA

0flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Construction

How much construction cost has been reported?

In EMBASSY CITADEL, ₹107.77 Cr of a declared ₹2184.43 Cr estimated project cost is reported as incurred, about 4.9%, as at the last certified filing with MahaRERA.

4.9%

₹107.77 Cr

of ₹2184.43 Cr declared cost

Cost incurred as last certified to MahaRERA. It is a financial measure, not a survey of site work, and it can lag on-site reality between filings.

Source · MahaRERA quarterly progress filing · read 12 Jul 2026

Sales

How much has actually been sold?

In EMBASSY CITADEL, 39 of 316 homes filed with MahaRERA are recorded as sold or booked (1 with registered agreements and 38 booked), about 12%, and 277 remain available.

12%sold

39 of 316 homes

₹786.85 Cr

committed by buyers

Counts and agreement value as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. Of that agreement value, ₹21.43 Cr (about 3%) is recorded as collected and ₹765.42 Cr as receivable.

Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026

What buyers actually paid: across 39 registered agreements, the effective carpet rate is ₹71,512/sqft, with eight in ten falling between ₹63,328 and ₹83,210 — computed from the agreement values and carpet areas the promoter filed, not broker quotes.

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing.

What the filings record, home by home

Read from MahaRERA on 20 September 2026

MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for the sold ones the registered agreement value — the consideration filed for that specific home. On this project 55 homes carry one, and 261 of the 316 are recorded unsold. Since we started watching this ledger, 22 homes have moved out of the unsold list, most recently on 12 September 2026.

Here is one of those unsold homes, priced against what buyers of the same home on other floors actually filed:

HomeCarpetFiled for the same home on other floorsBased on
17023,123 sqftRs 23.4743 cr typical, over Rs 19.8744 cr to Rs 24.9189 cr9 filed on this stack, floors 33–54

A filed consideration is what was registered for one home. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the home is available to you today. One of the two observations is an archived copy whose time is the moment the file was written, not a portal fetch time.

In EMBASSY CITADEL, 259 of the 261 unsold homes have agreements filed on their own stack. The Price Comparison Report gives each of them its own row — the filed agreements behind that stack listed in full, the government reckoner value the promoter filed against it, and whether it is mortgaged to a lender while still on the unsold list. Built from the filing itself, sent by email.

See the other 260 homes — ₹2,999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+84 and 158 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
NORTH + SOUTH WING(SALE)2G+84158-

Unit mix on the filing: 316 residential.

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at LOWER PAREL, DR. E. MOSES ROAD, Ward GSouth, Mumbai City, 400018. Per the filed land record, the plot is bounded to the north by KONARK TOWER, to the south by SHAH ANN NAR & APTE CHAWL, to the east by BLU TOWER C & D and to the west by DR. E. MOSES ROAD. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~1 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Lower Parel / Worli business district1 km
Nariman Point / Fort8 km
Bandra Kurla Complex (BKC)9 km
Chhatrapati Shivaji Int'l Airport11 km
Andheri MIDC / SEEPZ16 km
Powai / Hiranandani business park16 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Worli

DB Turf View
Deregistered by MahaRERA · possession by Dec 2026 · Turf Estate JV
THE Xclusiv
Not filing quarterly progress reports · possession by Dec 2026 · Om Omega Shelters
THE Legacy
possession by Mar 2027 · Sachiv Sahni
47 Race Course
Deregistered by MahaRERA · possession by Dec 2027 · Akshay Sthapatya Pvt. Ltd.
Nishuvi Rehab Phase
Deregistered by MahaRERA · possession by Dec 2027 · Nishuvi Corporation
SEA Face House, Worli
possession by Mar 2028 · Paroha Reality LLP

Major developers building in Worli

Other RERA-registered projects in Mumbai City

Emmanuel
possession by Dec 2026 · Skyline Realty Private Limited
Eon One
declared completion Jun 2026 · Firstlight Properties Private Limited
Essgee Options One Phase I
declared completion Dec 2023 · GMJ Builders & Developers
Esta Ranjit House
possession by Jun 2027 · Esta Ranjit House
Estoria Heights
declared completion Oct 2018 · Sanghvi Realtech PVT LTD
Eterna 275
possession by Dec 2029 · Eterna Lifespace LLP

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026