Mumbai/Project record

MahaRERA · the public record

FALCO RIVERSHIRE

Thane · AANYA REALTORS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Dec 2021declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2021

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51700005912

Delivery and registration

When is the project declared for completion?

FALCO RIVERSHIRE is registered with MahaRERA as P51700005912 and the promoter has declared completion for 30 Dec 2021.

30 Dec 2021

declared completion

57months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51700005912
Registered on14 Aug 2017
Promoter-declared completion30 Dec 2021
Current statusCertificate Signed
Against todayabout 57 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for FALCO RIVERSHIRE record 18 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 18 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Aanya Realtors is the promoter of record on 3 projects registered with MahaRERA, 1 of which carries a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

3projects

registered with MahaRERA

1flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for FALCO RIVERSHIRE in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+14.

BuildingWingsFloorsDeclared completion
FALCO RIVERSHRE1G+1431 Dec 2020

Legal and disputes

What disputes are disclosed?

11 complaints are on the MahaRERA record for FALCO RIVERSHIRE, with orders passed in 11 of them.

11complaints

11with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000000022729/08/2017Prasad Chaudhari vs Rohit Chuganiorder passed
CC00600000037501429/03/2023Manshad Abdul Rauf Shaikh vs Aanya Realtors (Rohit Iswar Chugani)order passed
CC00600000005570508/08/2018Bipin Rane vs Aanya Realtorsorder passed
CC00600000005570808/08/2018Rajesh Shingote vs Aanya Realtorsorder passed
CC00600000005577322/08/2018UNNIKRISHNAN VC vs AANYA REALTORSorder passed
CC00600000005634326/09/2018Mohini Motwani vs Aanya Realtorsorder passed
CC00600000005656418/10/2018JAIKISHIN CHAPRU vs AANYA REALTORSorder passed
CC00600000005666012/11/2018Nanda Jain & Ramkumar Kori vs M/S AANYA REALTORSorder passed
CC00600000005796518/03/2019RAMKUMAR KORI vs M/S AANYA REALTORS PVT LTDorder passed
CC00600000007920108/05/2019NAVIN ASHOK BOKARIA vs Aanya Realtorsorder passed
CC00600000018203631/12/2019Nitin Dhansingh Mahale vs Aanya Realtorsorder passed

Location, Land & Connectivity

Located at Kalyan, Thane, 421102. Per the filed land record, the plot is bounded to the north by SY NO 33 HISSA 4 PART, to the south by SY NO 33 HISSA NO 3, to the east by SY NO 29 and to the west by VACANT LAND. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~34 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park34 km
Andheri MIDC / SEEPZ37 km
Chhatrapati Shivaji Int'l Airport39 km
Bandra Kurla Complex (BKC)40 km
Lower Parel / Worli business district48 km
Nariman Point / Fort54 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Sandeep Ratan Patil is the promoter on 2 MahaRERA-registered projects, of which 2 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other RERA-registered projects in Ambivali West

Godrej Riviera Phase 1
possession by Dec 2026 · Godrej Properties Limited
Gaikwad Residency
possession by Dec 2026 · Niwara Group
Gangubai Height
possession by Dec 2026 · Vinayak Construction
Ashapura Galaxy
possession by Mar 2027 · Ashapura Estates
Lotus Residency
possession by Mar 2027 · Kulvinder Infrastructure Private Limited
Neptune Triveni Sangam
Developer in insolvency (NCLT) · possession by Jul 2027 · Neptune Developers Limited

Major developers building in Ambivali West

Other RERA-registered projects in Thane

Falcon
declared completion Jun 2018 · M/S Ace Constructions
Falcon Building No 58
possession by Apr 2028 · Roma Builders Private Limited
Fatima Enclave- A & B
possession by Mar 2027 · Rais Aziz Qureshi
Fatima Enclave- C Wing
possession by Mar 2027 · Rais Aziz Qureshi
Fatima Enclave- D Wing
possession by Mar 2027 · Rais Aziz Qureshi
Fatima Heights
declared completion Jun 2025 · Lfka Builders AND Developers

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026