MahaRERA Property Intelligence · Mumbai Suburban

galaxy royale

P51800010773 · promoter Realtors

Certificate SignedDue 30 Oct 2020

Delivery & Registration

MahaRERA registrationP51800010773
Registered on31 Aug 2017
Promoter-declared completion30 Oct 2020
Current statusCertificate Signed
Against todayabout 69 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+31.

BuildingWingsFloorsDeclared completion
GALAXY ROYALE1G+31-

Complaints & Orders

1 complaint is on the MahaRERA record for this project, with orders passed in 1. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC00600000019915225/11/2021Galaxy Royale CHSL (society) vs M R REALTORSorder passed

A co-operative housing society is the complainant here (Galaxy Royale CHSL) and MahaRERA has already passed an order. On a redevelopment, that is the LANDOWNER society in dispute with its developer — a different order of risk from a single buyer's grievance, because it can touch the development rights, the society's consent, and ultimately the title to your flat. Have your lawyer read this order and the development agreement together before you commit.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 2 times. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
30 Oct 202030 Apr 2020There is a reservation of maternity home in this SRA scheme, which was to be handed over to BMC. The said reservation has been completed and is ready to be handed over. Furthermore
30 Oct 202030 Apr 2020Some approvals pending from govt authorities

Location, Land & Connectivity

Located at Andheri, Mumbai Suburban, 400068. Per the filed land record, the plot is bounded to the north by D P ROAD, to the south by D P ROAD, to the east by RIDDHI SIDDHI CHS and to the west by TIRANGA CHS. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~15 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Andheri MIDC / SEEPZ15 km
Powai / Hiranandani business park17 km
Chhatrapati Shivaji Int'l Airport19 km
Bandra Kurla Complex (BKC)22 km
Lower Parel / Worli business district29 km
Nariman Point / Fort37 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

See every M R Realtors project & its RERA track record →

Other RERA-registered projects in Dahisar East

Sahakar Vista
possession by Jul 2026 · Sahakar Creation
Commercial Wing - NL Plaza And Residential Wing - NL Krishna
possession by Aug 2026 · Beautiful Properties Private Limited
Krishna Kripa
possession by Aug 2026 · Skyla Developers LLP
RAJ Capital
possession by Aug 2026 · RAJ Insignia Private Limited
Bhaveshwar Heights
possession by Sep 2026 · Shree Krishna Real Estate And Developers
Padma Apartment CO-Operative Housing Society Limited
possession by Sep 2026 · Haritara Construction Company Private Li

Major developers building in Dahisar East

Other RERA-registered projects in Mumbai Suburban

Gami And Jaydeep Elanza
declared completion Jun 2026 · M/S Real Infrastructure CO
Gami AND Jaydeep Elora
possession by Sep 2029 · M/S Real Infrastructure CO
Gami AND Jaydeep Estella
possession by Mar 2027 · M/S Real Infrastructure CO
Gami And Jaydeep Ventura Commercial Hub
possession by Oct 2026 · M/S Real Infrastructure CO
Ganapati Baug Chsl
possession by Jan 2028 · Nitai Gaur Enterprises
Ganesh Bhuvan CHS Ltd
possession by Dec 2027 · Shree Swami Samarth Developers (project

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026