Mumbai/Project record

MahaRERA · the public record

HAVA HIRA CHS

Mumbai Suburban · Patel Developers

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Apr 2023declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Apr 2023

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800012931

Delivery and registration

When is the project declared for completion?

HAVA HIRA CHS is registered with MahaRERA as P51800012931 and the promoter has declared completion for 30 Apr 2023.

30 Apr 2023

declared completion

41months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800012931
Registered on07 Sep 2017
Promoter-declared completion30 Apr 2023
Current statusCertificate Signed
Against todayabout 41 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for HAVA HIRA CHS record 24 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 24 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Patel Developers is the promoter of record on 175 projects registered with MahaRERA, 30 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

175projects

registered with MahaRERA

30flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for HAVA HIRA CHS in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+12.

BuildingWingsFloorsDeclared completion
Hava Hira CHS1G+12-

Legal and disputes

What disputes are disclosed?

12 complaints are on the MahaRERA record for HAVA HIRA CHS, with orders passed in 12 of them.

12complaints

12with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000002288013/01/2018VAHEEDA NARVEL vs HIFZUR REHMAN PATELorder passed
CC00600000005800309/02/2019ANANT SHANKAR PAWASKAR vs PATEL DEVELOPERorder passed
CC00600000014101825/09/2019Hava Hira Flat Purchasers Association vs Hava Hira Coop Housing Society Ltdorder passed
CC00600000019296017/03/2020SAKSHI SHASHANK PARAB vs PATEL DEVELOPERSorder passed
CC00600000019295817/03/2020VINODLAL POPATLAL SHAH vs PATEL DEVELOPERSorder passed
CC00600000019477502/11/2020Mr. Rajul B. Booch & Mrs. Moushmi R. Booch vs M/s Patel Developers & M/s Hava CHS Ltd.order passed
CC00600000039583229/05/2023KAMLA N CHANDRUMANIA vs M/s. Patel Developersorder passed
CC00600000039598829/05/2023RABIYAL HUSSAIN SHAIKH vs M/S. PATEL DEVELOPERSorder passed
CC00600000039598729/05/2023RAVEEN PUNJABI vs M/s. Patel Developersorder passed
CC1250021221/01/2025ANANT SHANKAR PAWASKAR vs Patel Developersorder passed
CC1250102026/03/2025Mayank Mehta vs Patel Developersorder passed
CC1250199518/06/2025Shakil sirajuddin Shaikh vs Patel Developersorder passed

Legal & Litigation

The promoter has declared 1 court case on this project to MahaRERA. 1 is still pending. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your home. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
High Court MumbaiCARBP/295/20172017Pending For Hearing

Location, Land & Connectivity

Located at Borivali, Mumbai Suburban, 400064. Per the filed land record, the plot is bounded to the north by 9 Mtr Road, to the south by Kantilal Gandhi, to the east by Ramrameshwar Bldg and to the west by Satya Niwas. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~7 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Andheri MIDC / SEEPZ7 km
Powai / Hiranandani business park10 km
Chhatrapati Shivaji Int'l Airport11 km
Bandra Kurla Complex (BKC)14 km
Lower Parel / Worli business district21 km
Nariman Point / Fort29 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Malad West

Shree Hari Krupa
possession by Sep 2026 · Mamtora Foundation
Shreeji Plaza Wing B
possession by Sep 2026 · Siddharth Enterprises
Linkpark
possession by Oct 2026 · Adarsh Industrial Estate Private Limited
Bhagat Grandeur
possession by Dec 2026 · Chirag Agro Fins Private Limited
Liberty Heights
possession by Dec 2026 · VP Casa Constructions LLP
Lovely Chs. LTD
possession by Dec 2026 · Jinam Realtors

Major developers building in Malad West

Other RERA-registered projects in Mumbai Suburban

Haware Amara
possession by Jan 2028 · Haware Amara LLP
Haware Intelligentia Sigma South Jvlr Wing C
declared completion Jun 2026 · Suresh Kashinath Haware
Haware Sky
possession by Feb 2029 · Haware SKY LLP
Heera Residency
possession by Mar 2029 · Apples Developers
Helios Apartments
possession by Jun 2030 · Cadcons Icons LLP
HEM Ratan Apartments AND Kamlesh Apartments
possession by Dec 2026 · NEW India Construction Company

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026