MahaRERA · the public record
HIGHLAND HAVEN BUILDING 6F MIST-B PHASE 5
Balkum · SIDDHI KRISH DEVELOPERS
Know the project.
Then choose your home.
The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.
The record · free to read
Registration read 12 Jul 2026Progress & dates
The timeline on file.
Available record
No construction trend to plot.
The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.
declared completion
31 Dec 2029
The registered date and a construction update answer different questions. Neither is a confirmation of possession.
MahaRERA registration · read 12 Jul 2026
From another project
See the report before you buy.
A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.
Read a sample report ↗The source record
The details behind the headline.
MahaRERA · P51700005341
Delivery and registration
When is the project declared for completion?
HIGHLAND HAVEN BUILDING 6F MIST-B PHASE 5 is registered with MahaRERA as P51700005341 and the promoter has declared completion for 31 Dec 2029.
31 Dec 2029
declared completion
39months to go
against the declared date
The completion date and status as they stand on the MahaRERA registration record.
Source · MahaRERA project registration · read 12 Jul 2026
| MahaRERA registration | P51700005341 |
| Registered on | 11 Aug 2017 |
| Promoter-declared completion | 31 Dec 2029 |
| Current status | Certificate Signed |
| Against today | 39 months to the declared date |
Approvals and compliance
What compliance filings are on record?
MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for HIGHLAND HAVEN BUILDING 6F MIST-B PHASE 5 record 34 quarterly progress reports since registration.
34quarterly filings
Entries as they appear on MahaRERA's own lists and the project's progress filing.
Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026
- Filing progress reports — 34 quarterly progress reports on record since registration, with no current default.
Construction
How much construction cost has been reported?
In HIGHLAND HAVEN BUILDING 6F MIST-B PHASE 5, ₹55.20 Cr of a declared ₹185.00 Cr estimated project cost is reported as incurred, about 29.8%, as at the last certified filing with MahaRERA.
29.8%
₹55.20 Cr
of ₹185.00 Cr declared cost
Cost incurred as last certified to MahaRERA. It is a financial measure, not a survey of site work, and it can lag on-site reality between filings.
Source · MahaRERA quarterly progress filing · read 12 Jul 2026
Sales
How much has actually been sold?
In HIGHLAND HAVEN BUILDING 6F MIST-B PHASE 5, 90 of 402 homes filed with MahaRERA are recorded as sold or booked (67 with registered agreements and 23 booked), about 22%, and 312 remain available.
22%sold
90 of 402 homes
₹73.84 Cr
committed by buyers
Counts and agreement value as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. Of that agreement value, ₹27.72 Cr (about 38%) is recorded as collected and ₹46.11 Cr as receivable. The project registers 413 homes in total, while this sold/unsold inventory filing covers 402 of them.
Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026
What buyers actually paid: across 90 registered agreements, the effective carpet rate is ₹15,452/sqft, with eight in ten falling between ₹14,585 and ₹16,514 — computed from the agreement values and carpet areas the promoter filed, not broker quotes.
The inventory filing also declares: 11 reserved.
What the filings record, home by home
Read from MahaRERA on 13 September 2026
MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for the sold ones the registered agreement value — the consideration filed for that specific home. On this project 125 homes carry one, and 288 of the 413 are recorded unsold. Since we started watching this ledger, 35 homes have moved out of the unsold list, most recently on 04 September 2026.
Here is one of those unsold homes, priced against what buyers of the same home on other floors actually filed:
| Home | Carpet | Filed for the same home on other floors | Based on |
|---|---|---|---|
| SHOP NO 15 | 587 sqft | Rs 15,485 a sq ft typical, over Rs 13,099 to Rs 17,190 | 75 filed at this size |
A filed consideration is what was registered for one home. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the home is available to you today. One of the two observations is an archived copy whose time is the moment the file was written, not a portal fetch time.
In HIGHLAND HAVEN BUILDING 6F MIST-B PHASE 5, 278 of the 288 unsold homes have agreements filed on their own stack. The Price Comparison Report gives each of them its own row — the filed agreements behind that stack listed in full, the government reckoner value the promoter filed against it, and whether it is mortgaged to a lender while still on the unsold list. Built from the filing itself, sent by email.
Buildings & Wings
The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+44 and 413 homes are registered across the project.
| Building | Wings | Floors | Homes | Declared completion |
|---|---|---|---|---|
| BUILDING 6F- MIST B | 1 | G+44 | 413 | - |
Unit mix on the filing: 403 residential and 10 non-residential (shops/offices).
Legal and disputes
What disputes are disclosed?
1 complaint is on the MahaRERA record for HIGHLAND HAVEN BUILDING 6F MIST-B PHASE 5, with orders passed in 1 of them.
1complaint
1with an order
Counts as disclosed in the project record.
Source · MahaRERA project disclosures · read 12 Jul 2026
| Complaint no. | Filed | Parties | Status |
|---|---|---|---|
| CC006000000058117 | 19/02/2019 | Ambika Yuvraj Kololagi vs SIDDHI KRISH DEVELOPERS | order passed |
Legal & Litigation
The promoter has declared 3 court cases on this project to MahaRERA. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your home. This is declared by the promoter; there may be further cases not on the RERA record.
| Court | Case no. | Year | Status |
|---|---|---|---|
| Seventh Joint Cjsd | 607 | 2011 | For Evidence |
| Cjsd Thane | 435 | 2018 | Disposed Off Against Promoter |
| Civil Judge Senior Division Thane | 607 | 2011 | Ongoing |
Deadline Extensions
The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.
| From | Extended to | Stated reason |
|---|---|---|
| as registered | 31 Dec 2029 | In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various r |
Location, Land & Connectivity
Located at Balkum, Saket Road, Thane, Thane, 400608. Per the filed land record, the plot is bounded to the north by 20 M WIDE DP ROAD, to the south by S N 75-8, to the east by 15 M WIDE DP ROAD and to the west by MIST-A. These are the boundaries as recorded in the filed land record.
Location & connectivity
The nearest major job hub is ~15 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.
| Landmark | Straight-line |
|---|---|
| Powai / Hiranandani business park | 15 km |
| Andheri MIDC / SEEPZ | 16 km |
| Chhatrapati Shivaji Int'l Airport | 20 km |
| Bandra Kurla Complex (BKC) | 21 km |
| Lower Parel / Worli business district | 30 km |
| Nariman Point / Fort | 37 km |
Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.