19units filed as unsoldInventory · 13 September 2026
31 Dec 2025declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2025

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51700006307

Delivery and registration

When is the project declared for completion?

HIGHLAND SPRINGS B4- C WING is registered with MahaRERA as P51700006307 and the promoter has declared completion for 31 Dec 2025.

31 Dec 2025

declared completion

9months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51700006307
Registered on14 Aug 2017
Promoter-declared completion31 Dec 2025
Current statusCertificate Signed
Against todayabout 9 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for HIGHLAND SPRINGS B4- C WING record 34 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

What the filings record, home by home

Read from MahaRERA on 13 September 2026

MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for the sold ones the registered agreement value — the consideration filed for that specific home. On this project 183 homes carry one, and 19 of the 202 are recorded unsold.

Here is one of those unsold homes, priced against what buyers of the same home on other floors actually filed:

HomeCarpetFiled for the same home on other floorsBased on
1006365 sqftRs 52.68 lakh typical, over Rs 38.83 lakh to Rs 66.61 lakh16 filed on this stack, floors 1–17

A filed consideration is what was registered for one home. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the home is available to you today. Only one observation of this ledger so far: no change can be reported yet.

In HIGHLAND SPRINGS B4- C WING, every one of the 19 unsold homes has agreements filed on its own stack. The Price Comparison Report gives each of them its own row — the filed agreements behind that stack listed in full, the government reckoner value the promoter filed against it, and whether it is mortgaged to a lender while still on the unsold list. Built from the filing itself, sent by email.

See the other 18 homes — ₹2,999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+26.

BuildingWingsFloorsDeclared completion
HIGHLAND SPRINGS - C WING1G+26-

Legal and disputes

What disputes are disclosed?

3 complaints are on the MahaRERA record for HIGHLAND SPRINGS B4- C WING, with orders passed in 3 of them.

3complaints

3with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC1250251121/07/2025Amruta Kinjawadekar vs SIDDHI REAL ESTATE DEVELOPERSorder passed
CC1250251221/07/2025Sushil Jadhav vs SIDDHI REAL ESTATE DEVELOPERSorder passed
CC1260071708/02/2026PARESH MAHADEO MALVANKAR vs SIDDHI REAL ESTATE DEVELOPERSorder passed

Legal & Litigation

The promoter has declared 8 court cases on this project to MahaRERA. 4 are still pending. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your home. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Thane Civil Court1942009Dispossed Off
Thane Civil Court7912010Disposed Off
Thane Civil Court652017Pending
Thane Civil Court4262017Pending
Thane Civil Court482022Hearing Of Exhibit
Thane Civil Court232021Pending
High Court2412023Dispossed Off
Supreme Court Of IndiaDairy no 104992024Pending

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 2 times, as recorded on the register.

FromExtended toStated reason
as registered30 Nov 2024Project has been completed around 70% till October 2023. However, due to shortage of materials and non – availability of labour we are unable to finish the project before 30th De
30 Nov 202431 Dec 2025I, hereby apply for extension as per Order No. 40 Dated 27/12/2022 of the registered project bearing vide no P51700006307. As per HEARING DATED 11th August 2025, Hon'ble Shri Manoj

Location, Land & Connectivity

Located at Dhokali, University Road, Thane, Thane, 400608. Per the filed land record, the plot is bounded to the north by 20 mtr Wide DP Road, to the south by Podium, to the east by Wing-D and to the west by Wing-B. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~14 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Powai / Hiranandani business park14 km
Andheri MIDC / SEEPZ16 km
Chhatrapati Shivaji Int'l Airport19 km
Bandra Kurla Complex (BKC)21 km
Lower Parel / Worli business district30 km
Nariman Point / Fort37 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Siddhi Real Estate Developers is the promoter on 6 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by Siddhi Real Estate Developers

Siddhi Real Estate Developers
FlaggedThane
Siddhi Real Estate Developers
FlaggedThane

Other RERA-registered projects in Balkum

Dosti West County - Dosti Tulip
possession by Oct 2026 · Dosti Enterprises
Highland Springs B4 D Wing
possession by Dec 2026 · Siddhi Real Estate Developers
Mahavir Bliss
possession by Dec 2026 · M/s. Shivshakti Engineers
Shraddha Peninsula
possession by Dec 2026 · Padmagriha Heights
Sumeet Elite
possession by May 2027 · Vedant Construction
Dosti West County - Dosti Nest - Phase 1
possession by Jun 2027 · Dosti Enterprises

Major developers building in Balkum

Other RERA-registered projects in Thane

Highland Springs B4 D Wing
possession by Dec 2026 · Siddhi Real Estate Developers
Hill Crest
declared completion Sep 2024 · Universal Infra
Hill Park Co-Operative Housing Society Limited
possession by Aug 2028 · Unigrow On Infrastructure Housing LLP
Hill Side Residency Wing A B AND C
declared completion Dec 2024 · Supreme Developers
Hill Spring
declared completion Aug 2026 · Asha Infratech
Hillcrest
declared completion Dec 2023 · Siddhgiri Infra

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026