MahaRERA Property Intelligence · Thane
P51700006307 · Dhokali · promoter Siddhi Real Estate
| MahaRERA registration | P51700006307 |
| Registered on | 14 Aug 2017 |
| Promoter-declared completion | 31 Dec 2025 |
| Current status | Certificate Signed |
| Against today | about 7 months past the declared date |
MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.
The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+26.
| Building | Wings | Floors | Declared completion |
|---|---|---|---|
| HIGHLAND SPRINGS - C WING | 1 | G+26 | - |
3 complaints are on the MahaRERA record for this project, with orders passed in 3. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.
| Complaint no. | Filed | Parties | Status |
|---|---|---|---|
| CC12502511 | 21/07/2025 | Amruta Kinjawadekar vs SIDDHI REAL ESTATE DEVELOPERS | order passed |
| CC12502512 | 21/07/2025 | Sushil Jadhav vs SIDDHI REAL ESTATE DEVELOPERS | order passed |
| CC12600717 | 08/02/2026 | PARESH MAHADEO MALVANKAR vs SIDDHI REAL ESTATE DEVELOPERS | order passed |
The promoter has declared 8 court cases on this project to MahaRERA. 4 are still pending. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your flat. This is declared by the promoter; there may be further cases not on the RERA record.
| Court | Case no. | Year | Status |
|---|---|---|---|
| Thane Civil Court | 194 | 2009 | Dispossed Off |
| Thane Civil Court | 791 | 2010 | Disposed Off |
| Thane Civil Court | 65 | 2017 | Pending |
| Thane Civil Court | 426 | 2017 | Pending |
| Thane Civil Court | 48 | 2022 | Hearing Of Exhibit |
| Thane Civil Court | 23 | 2021 | Pending |
| High Court | 241 | 2023 | Dispossed Off |
| Supreme Court Of India | Dairy no 10499 | 2024 | Pending |
The promoter has had the MahaRERA completion deadline formally extended 2 times. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.
| From (declared) | To (revised) | Stated reason |
|---|---|---|
| 30 Nov 2024 | 30 Nov 2024 | Project has been completed around 70% till October 2023. However, due to shortage of materials and non – availability of labour we are unable to finish the project before 30th De |
| 30 Dec 2023 | 31 Dec 2025 | I, hereby apply for extension as per Order No. 40 Dated 27/12/2022 of the registered project bearing vide no P51700006307. As per HEARING DATED 11th August 2025, Hon'ble Shri Manoj |
Located at Dhokali, University Road, Thane, Thane, 400608. Per the filed land record, the plot is bounded to the north by 20 mtr Wide DP Road, to the south by Podium, to the east by Wing-D and to the west by Wing-B. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.
The nearest major job hub is ~14 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.
| Landmark | Straight-line |
|---|---|
| Powai / Hiranandani business park | 14 km |
| Andheri MIDC / SEEPZ | 16 km |
| Chhatrapati Shivaji Int'l Airport | 19 km |
| Bandra Kurla Complex (BKC) | 21 km |
| Lower Parel / Worli business district | 30 km |
| Nariman Point / Fort | 37 km |
Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.
🔒 The verdict & buyer playbook · Compliance report
The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.
🔒 Unit-by-unit guidance · Unit Guidance report
Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.
🔒 Full financial records — escrow, funding & the document catalog · Compliance report
The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.
Should you buy in HIGHLAND SPRINGS B4- C WING?
This page is the free MahaRERA filing summary. The full RERA Property Intelligence Report gives you the full regulatory standing, declared court litigation, buyer-complaint and adjudication history, quarterly-progress-report discipline, the builder's MahaRERA-wide track record, the building/tower breakdown, and the sanctioned layout plan. See a real one first:
Sample: Lodha Kandivali – Tower 2 → · browse all sample reports →
Compliance Report · ₹999
The regulator’s filing record, read · 1 working day
Scan with any UPI app to pay · quietlist@kotak
Unit Guidance Report · ₹2,999
Everything, down to which unit · 1 working day
Not useful to your decision? Full refund — no questions asked.
Scan with any UPI app to pay · quietlist@kotak
Paying from outside India? Pay $15 (Compliance) or $39 (Unit Guidance) via PayPal, or email hello@quietlist.in for a card invoice. Prefer to talk first, or have a portfolio to check? Same address. An information aid for your own due diligence, not legal or investment advice.
Free · Watch this project
We'll email you when this project's RERA record changes.
Siddhi Real Estate Developers is the promoter on 6 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).
Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.
Last checked against the RERA register: 27 Jul 2026