MahaRERA Property Intelligence · Thane

HIGHLAND SPRINGS B4- B WING

P51700007745 · Dhokali · promoter Siddhi Real Estate

Certificate SignedDue 30 May 2024

Delivery & Registration

MahaRERA registrationP51700007745
Registered on17 Aug 2017
Promoter-declared completion30 May 2024
Current statusCertificate Signed
Against todayabout 26 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+28.

BuildingWingsFloorsDeclared completion
HIGHLAND SPRINGS - B WING1G+2830 Jun 2022

Complaints & Orders

4 complaints are on the MahaRERA record for this project, with orders passed in 4. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC00600000019748604/07/2021Vinayak S. Narayane vs M/s. Siddhi Real Estate Developersorder passed
CC00600000019843123/09/2021Sandesh Rajdhar Chavan vs Partnerorder passed
CC00600000039776417/11/2023SHRIKANT VITHAL CHENNA vs Siddhi Real Estate Developersorder passed
CC00600000050052825/05/2024M/s Siddhi Real Estate Developers vs SHRIKANT VITHAL CHENNAorder passed

Legal & Litigation

The promoter has declared 5 court cases on this project to MahaRERA. 4 are still pending. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your flat. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Thane Civil Court7912010Pending
Thane Civil Court652017Pending
Thane Civil Court4262017Pending
Thane Civil Court1942009Dispossed Off
Thane Civil Court232021Pending

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
30 May 202430 May 2024The Project have been completed around 80 % till March 2023 and it is now pending for service of Lift. However, due to shortage of materials and non-availability of labour for elev

Location, Land & Connectivity

Located at Dhokali, University Road, Thane, Thane, 400608. Per the filed land record, the plot is bounded to the north by 20 mtr wide DP Road, to the south by wing-A, to the east by wing-c and to the west by 25 mtr wide DP Road. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~14 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Powai / Hiranandani business park14 km
Andheri MIDC / SEEPZ16 km
Chhatrapati Shivaji Int'l Airport19 km
Bandra Kurla Complex (BKC)21 km
Lower Parel / Worli business district30 km
Nariman Point / Fort37 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Siddhi Real Estate Developers is the promoter on 6 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by Siddhi Real Estate Developers

Siddhi Real Estate Developers
FlaggedThane
Siddhi Real Estate Developers
FlaggedThane
Siddhi Real Estate Developers
FlaggedThane
Siddhi Real Estate Developers
FlaggedThane
Siddhi Real Estate Developers
FlaggedThane

Other RERA-registered projects in Balkum

Dosti West County - Dosti Tulip
possession by Oct 2026 · Dosti Enterprises
Highland Springs B4 D Wing
possession by Dec 2026 · Siddhi Real Estate Developers
Mahavir Bliss
possession by Dec 2026 · M/s. Shivshakti Engineers
Shraddha Peninsula
possession by Dec 2026 · Padmagriha Heights
Sumeet Elite
possession by May 2027 · Vedant Construction
Dosti West County - Dosti Nest - Phase 1
possession by Jun 2027 · Dosti Enterprises

Major developers building in Balkum

Other RERA-registered projects in Thane

Highland Springs B4- C Wing
declared completion Dec 2025 · Siddhi Real Estate Developers
Highland Springs B4 D Wing
possession by Dec 2026 · Siddhi Real Estate Developers
Highland Springs B4- E Wing
declared completion Oct 2019 · Siddhi Real Estate Developers
Hill Crest
declared completion Sep 2024 · Universal Infra
Hill Galaxy
declared completion Jun 2022 · R R Builders
Hill Galaxy Phase II
possession by Jun 2030 · Gulamrasul Mohammed ALI Shaikh

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026