MahaRERA Property Intelligence · Palghar

IPSIT PARADISE PHASE 1

P99000011163 · promoter Dreamland Developers

Certificate SignedDue 30 Dec 2025

Delivery & Registration

MahaRERA registrationP99000011163
Registered on31 Aug 2017
Promoter-declared completion30 Dec 2025
Current statusCertificate Signed
Against todayabout 7 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Dreamland Developers is the promoter of record on 7 projects, of which none currently carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+2.

BuildingWingsFloorsDeclared completion
IPSIT PARADISE PHASE 11G+230 Jun 2018

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Legal & Litigation

The promoter has declared 4 court cases on this project to MahaRERA. 1 is still pending. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your flat. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Cosumer Dispute Redressal Commission State Of Maharashtra3762015Interim Order Not To Creaate Third Party Right
Consumer Disput Redressal Commision State Of Maharashtra3812015Interim Order Not To Create Third Party Right
Lower Court Of Vasai3002010Developer Have Won In Lower Court In July
Lower Court Of Vasai5952010Pending

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
30 Dec 202531 Dec 2024DUE TO SHORTAGE OF MATERIALS AND SAND WE WERE NOT ABLE TO GET THE PROJECT COMPLETED ON TIME. WE WERE NOT ABLE TO GIVE POSSESSION TO THE CLIENT. THEREFORE WE WOULD LIKE TO REQUEST Y

Location, Land & Connectivity

Located at Borivali, Mumbai Suburban, 401209. Per the filed land record, the plot is bounded to the north by VIRAR KAVER STATE HIGHWAY, to the south by LAND OF MR SAMANT, to the east by INTERNAL LAYOUT ROAD and to the west by NALLA. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~39 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Andheri MIDC / SEEPZ39 km
Powai / Hiranandani business park40 km
Chhatrapati Shivaji Int'l Airport43 km
Bandra Kurla Complex (BKC)46 km
Lower Parel / Worli business district54 km
Nariman Point / Fort62 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Dreamland Developers is the promoter on 3 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by Dreamland Developers

Dreamland Developers
FlaggedThane
Dreamland Developers
FlaggedPalghar

Other RERA-registered projects in Nallasopara East

Gharkul
possession by Aug 2026 · Achole Infra LLP
Freny Avenue
possession by Aug 2026 · Sumitra Realtors
Model Cooperative Housing Society LTD
possession by Oct 2026 · Sai Vaishnav Infra Llp
N G Platinum City
possession by Dec 2026 · J M G Realtors PVT LTD
NEW ERA
possession by Dec 2026 · Crystal Realty
Rudra Heights Bldg NO 1 Wing -G
possession by Dec 2026 · Aura Navkar Developers

Major developers building in Nallasopara East

Other RERA-registered projects in Palghar

Ipsit Paradise Phase 2
declared completion Apr 2026 · Dreamland Developers
Ipsit Sukhanand
possession by Dec 2027 · Incline Realtors
IRA Forming Part OF THE Complex Akhand
possession by Dec 2027 · Techton Lifespaces LLP
Irasa Park Phase 1
possession by Dec 2027 · Suburban Spaces LLP
Irasa Park Phase 2
declared completion Dec 2023 · Suburban Spaces LLP
ISA Forming THE Part OF Complex Akhand
possession by Jun 2028 · Techton Lifespaces LLP

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026