IRENE WING A PHASE 1

MALAD WEST · Sheth Creators and Sunvision Private Limited

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Dec 2025declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2025

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800015507

Delivery and registration

When is the project declared for completion?

IRENE WING A PHASE 1 is registered with MahaRERA as P51800015507 and the promoter has declared completion for 30 Dec 2025.

30 Dec 2025

declared completion

9months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800015507
Registered on07 Mar 2018
Promoter-declared completion30 Dec 2025
Current statusCertificate Signed
Against todayabout 9 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for IRENE WING A PHASE 1 record 32 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Promoter record

What else is this promoter on record for?

Sheth Creators is the promoter of record on 4 projects registered with MahaRERA, none of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

4projects

registered with MahaRERA

0flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for IRENE WING A PHASE 1 in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+67.

BuildingWingsFloorsDeclared completion
IRENE WING A PHASE 11G+67-

Legal and disputes

What disputes are disclosed?

5 complaints are on the MahaRERA record for IRENE WING A PHASE 1, with orders passed in 5 of them.

5complaints

5with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000009009115/07/2019deepak keni vs sheth creators and sun vision pvt ltdorder passed
CC00600000059142404/08/2024Sidharth Dhanjani vs Sheth Creators and Sunvision Private Limitedorder passed
CC00600000030310419/10/2022Sheth Creators and Sun Vision Pvt. Ltd. Sheth Creators and Sun Vision Pvt. Ltd. vs Mr. Sumit Anil Shrivastavaorder passed
CC00600000048006813/04/2024vicky madanmohan gupta vs SHETH CREATORS & SUN-VISION PRIVATE LIMITEDorder passed
CC1260042523/01/2026Sheth Creators and Sunvision Private Limited vs Ganesh Bamnoteorder passed

Legal & Litigation

The promoter has declared 7 court cases on this project to MahaRERA. 7 are still pending. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your home. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Mumbai High Court71902016Pending
Bombay City Civil Court11622016Pending
Mumbai High Court10162012Pending
Honerable Court Of Sessions For Borivali Division Goregaon Bombay2002742016Pending
Additional Chief Metropolitan Magistrates Twentyfourth Court802010Pending
Additional Chief Metropolitan Magistrates Twentyfourth CourtSS/24005132010Pending
Bombay City Civil Court3312018Pending

Location, Land & Connectivity

Located at MALAD WEST, NEAR MITTAL COLLEGE, Andheri, Mumbai Suburban, 400064. Per the filed land record, the plot is bounded to the north by JAGAMAGIA CENTRE, to the south by IRENE WING B, to the east by REHAB BUILDING and to the west by R G NO 2. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~7 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Andheri MIDC / SEEPZ7 km
Powai / Hiranandani business park10 km
Chhatrapati Shivaji Int'l Airport11 km
Bandra Kurla Complex (BKC)14 km
Lower Parel / Worli business district21 km
Nariman Point / Fort29 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Sheth Creators And Sunvision Private Limited is the promoter on 2 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by Sheth Creators And Sunvision Private Limited

Sheth Creators And Sunvision Private Limited
FlaggedMumbai Suburban

Other RERA-registered projects in Malad West

Shree Hari Krupa
possession by Sep 2026 · Mamtora Foundation
Shreeji Plaza Wing B
possession by Sep 2026 · Siddharth Enterprises
Linkpark
possession by Oct 2026 · Adarsh Industrial Estate Private Limited
Bhagat Grandeur
possession by Dec 2026 · Chirag Agro Fins Private Limited
Liberty Heights
possession by Dec 2026 · VP Casa Constructions LLP
Lovely Chs. LTD
possession by Dec 2026 · Jinam Realtors

Major developers building in Malad West

Other RERA-registered projects in Mumbai Suburban

Irene Wing B Phase 1
possession by Oct 2028 · Sheth Creators And Sunvision Private Lim
Iris Business Park
declared completion Dec 2022 · Iris Business Park
Isha Vasyam
possession by Jun 2027 · Jyoti Sagar Corporation
Ishaan Enclave
possession by Mar 2027 · Ishaan Developers
Isle OF Calm Tower 1
possession by Mar 2029 · Sunrise Housing
Isle OF Calm Tower 2
possession by Mar 2029 · Sunrise Housing

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026