Jaywant Villa Co.operative Housing Society Ltd

Mumbai Suburban · MAHENDRA MADHUKAR SAWANT

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

01 Dec 2019declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

01 Dec 2019

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800012578

Delivery and registration

When is the project declared for completion?

Jaywant Villa Co.operative Housing Society Ltd is registered with MahaRERA as P51800012578 and the promoter has declared completion for 01 Dec 2019.

01 Dec 2019

declared completion

81months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800012578
Registered on04 Sep 2017
Promoter-declared completion01 Dec 2019
Current statusCertificate Signed
Against todayabout 81 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Jaywant Villa Co.operative Housing Society Ltd record 10 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 10 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Mahendra Madhukar Sawant is the promoter of record on 72 projects registered with MahaRERA, 13 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

72projects

registered with MahaRERA

13flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Jaywant Villa Co.operative Housing Society Ltd in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8.

BuildingWingsFloorsDeclared completion
Jaywant Villa Co-operative Housing Society Ltd1G+8-

Legal and disputes

What disputes are disclosed?

6 complaints are on the MahaRERA record for Jaywant Villa Co.operative Housing Society Ltd, with orders passed in 6 of them.

6complaints

6with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000020984705/02/2022JATIN DESAI vs M/s AKSHAY STHAPATYAorder passed
CC00600000022094326/04/2022Dilip Joshi vs Mahendra Madukar Sawantorder passed
CC00600000023113604/06/2022Punit Ramakrishna Walawalkar vs Mahendra Madhukar Sawantorder passed
CC00600000023119427/05/2022Harsha Umesh Khot vs Mahendra Madhukar Sawantorder passed
CC00600000023127127/05/2022Prabhakar Harishchandra Mhatre vs Mahendra Madhukar Sawantorder passed
CC00600000025143012/07/2022Rahul Ashok Abhyankar vs Mahendra Madhukar Sawantorder passed

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered01 Dec 2019The project is of stilt + 6th Floors & 7Th part, presently we have secured the permission till 5th floor and have accordingly built the building. The permission for upper 1½ floor

Location, Land & Connectivity

Located at Andheri, Mumbai Suburban, 400063. Per the filed land record, the plot is bounded to the north by Sarthak CHS Ltd , to the south by Vijaya Bunglows, to the east by CTS 332 and to the west by H N Purav Marg. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~4 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Andheri MIDC / SEEPZ4 km
Powai / Hiranandani business park8 km
Chhatrapati Shivaji Int'l Airport8 km
Bandra Kurla Complex (BKC)11 km
Lower Parel / Worli business district19 km
Nariman Point / Fort27 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Goregaon East

Matrusmruti
possession by Oct 2026 · Gio Properties
Samarth Nandadeep Heights
possession by Oct 2026 · Samarth Tsquare
Onyx
possession by Nov 2026 · Shreeram Builders
Goregaon Adwait Chsl - Vijay Sadan
possession by Dec 2026 · Prashant Shirsat
Agarwal Floresta - Maple
possession by Dec 2026 · Homewell Realty LLP
Ashwin Heights
possession by Dec 2026 · Westinrely Developers PVT LTD

Major developers building in Goregaon East

Other RERA-registered projects in Mumbai Suburban

JD Pride Business Park
possession by May 2028 · Dennis James Fernandes
JDJ Jewel
possession by Jan 2031 · JDJ Housing
JDN Aura
possession by Mar 2030 · JDN Developers
JDN Cornerstone
possession by Dec 2029 · JDN Builders LLP
Jeandveekedarnath
possession by Dec 2026 · JE AND VEE Infrastructure
Jeevan Shobha Chsl AND Bhansali Chsl
declared completion Mar 2026 · Hirani Realtors LLP

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.