Mumbai/Project record

MahaRERA · the public record

KAKAD HEIGHTS

BANDRA WEST · NIRAJ KAKAD CONSTRUCTIONS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Jan 2021declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Jan 2021

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800010226

Delivery and registration

When is the project declared for completion?

KAKAD HEIGHTS is registered with MahaRERA as P51800010226 and the promoter has declared completion for 30 Jan 2021.

30 Jan 2021

declared completion

68months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800010226
Registered on24 Aug 2017
Promoter-declared completion30 Jan 2021
Current statusCertificate Signed
Against todayabout 68 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for KAKAD HEIGHTS record 15 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 15 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Niraj Kakad Constructions is the promoter of record on 35 projects registered with MahaRERA, 6 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

35projects

registered with MahaRERA

6flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for KAKAD HEIGHTS in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+15.

BuildingWingsFloorsDeclared completion
KAKAD HEIGHTS1G+15-

Legal and disputes

What disputes are disclosed?

1 complaint is on the MahaRERA record for KAKAD HEIGHTS, with orders passed in 1 of them.

1complaint

1with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000007849116/03/2019Lakshman Joukani vs Niraj Kakad Constructionorder passed

Legal & Litigation

The promoter has declared 1 court case on this project to MahaRERA. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your home. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
High Court470 of 20172017Consent Terms

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered30 Jul 2020Disputes with the Financial Institution IDFC First Bank Ltd. (formerly known as Capital First Ltd.) and numerous frivolous litigations filed by the said Financial Institution.

Location, Land & Connectivity

Located at BANDRA WEST, Junction of 25th and 29th Road, Andheri, Mumbai Suburban, 400050. Per the filed land record, the plot is bounded to the north by 29TH ROAD, to the south by FINAL PLOT NO 128, to the east by 25TH ROAD and to the west by FINAL PLOT NO 127A. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~4 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Bandra Kurla Complex (BKC)4 km
Chhatrapati Shivaji Int'l Airport5 km
Lower Parel / Worli business district7 km
Andheri MIDC / SEEPZ9 km
Powai / Hiranandani business park10 km
Nariman Point / Fort15 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Niraj Kakad Constructions is the promoter on 2 MahaRERA-registered projects, of which 2 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by Niraj Kakad Constructions

Niraj Kakad Constructions
Past its declared completion dateMumbai Suburban

Other RERA-registered projects in Bandra West

Bandra Boon CHS LTD
possession by Sep 2026 · Mass Jaks Associate Ventures
Aryan Tower
Not filing quarterly progress reports · possession by Dec 2026 · Suchit Developers
Brightland
possession by Dec 2026 · Sambhavparshva Developers Private Limite
Hill Casa
possession by Dec 2026 · Husain Taher Patni
Hill View
possession by Dec 2026 · L Nagpal Builders LLP
Manthan Embassy
possession by Dec 2026 · Manthan Development Corporation

Major developers building in Bandra West

Other RERA-registered projects in Mumbai Suburban

Kakkad
possession by Dec 2026 · Silver Land Developers Private Limited
Kalpak
declared completion Jun 2024 · A P Properties
Kalpana Sangam
declared completion Sep 2023 · Srushti Sangam Builders PVT LTD
Kalpana Srushti
declared completion Sep 2023 · Chinnaiah Venkatesh Gowda
Kalpataru Advay
possession by Jun 2030 · Kalpataru Limited
Kalpataru Amare
possession by Dec 2027 · Kalpataru Limited

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026