MahaRERA Property Intelligence · Mumbai Suburban

DEVI KAKAD SOLITAIRE

P51800010010 · Sindhi Society · promoter Niraj Kakad Constructions

Certificate SignedDue 29 Dec 2020

Delivery & Registration

MahaRERA registrationP51800010010
Registered on23 Aug 2017
Promoter-declared completion29 Dec 2020
Current statusCertificate Signed
Against todayabout 67 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Niraj Kakad Constructions is the promoter of record on 34 projects, of which 6 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+15.

BuildingWingsFloorsDeclared completion
DEVI KAKAD SOLITAIRE1G+15-

Complaints & Orders

3 complaints are on the MahaRERA record for this project, with orders passed in 3. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC00600000005772515/03/2019Sneha Sachhanand Tejwani vs Niraj Kakad Constructionsorder passed
CC00600000000119730/10/2017Richbond Finvest Services Pvt. Ltd. vs Niraj Kakad Constructionsorder passed
CC00600000019515905/12/2020Niraj Kakad HUF vs Sneha Sachhanand Tejwaniorder passed

Legal & Litigation

The promoter has declared 3 court cases on this project to MahaRERA. 1 is still pending. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your flat. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Bombay Highcourt392016The Lessee Has Illegally Terminated The Development Agreement And The Said Matter Is In Arbitration
High Court470 of 20172017Consent Terms
Bombay High Court8002019Pending

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
29 Dec 202029 Jun 2020The Arbitrator has upheld the termination of the Development Agreement which was executed with the lessee, vide order dated 26th April, 2019. However we are in the process of filin

Location, Land & Connectivity

Located at Sindhi Society, Road No. 2, Andheri, Mumbai Suburban, 400071. Per the filed land record, the plot is bounded to the north by CTS NO 214, to the south by EXISTING ROAD, to the east by CTS NO 216 and to the west by CTS NO 212. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~3 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Bandra Kurla Complex (BKC)3 km
Chhatrapati Shivaji Int'l Airport5 km
Powai / Hiranandani business park7 km
Andheri MIDC / SEEPZ9 km
Lower Parel / Worli business district10 km
Nariman Point / Fort17 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Niraj Kakad Constructions is the promoter on 2 MahaRERA-registered projects, of which 2 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by Niraj Kakad Constructions

Niraj Kakad Constructions
Past its declared completion dateMumbai Suburban

Other RERA-registered projects in Chembur

Chembur Deep Jyoti CHS LTD
possession by Jul 2026 · P M Developers
Hubtown Seasons - B Wing
possession by Jul 2026 · Joynest Premises Privatelimited
Gurukripa
possession by Sep 2026 · Inspira Realty And Infra Private Limited
Kranti Heights
possession by Sep 2026 · Sidhivinayak Constructions
Mass Metropolis
possession by Sep 2026 · Grace Urban Development Corporation
Mohite Mrugank
possession by Sep 2026 · Mohite Infraprojects Private Limited

Major developers building in Chembur

Other RERA-registered projects in Mumbai Suburban

Devika Tower
declared completion Jun 2024 · Braj Raj Singh
Devikunj CO-Operative Housing Society Limited
possession by Dec 2027 · Yogiraj Builders AND Developers
Devine Mercy SRA CHS Prop
declared completion Apr 2023 · Mahesh Rajaram Mestry
Devki Nagar CHS LTD
possession by Dec 2027 · MS Infrastructure
Devkrupa CO-Operative Society LTD
declared completion Jun 2025 · Shree Jalaram Builders & Developers
Devraj Residency
declared completion Jun 2026 · Shams Entreprises

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026