KAPADIA AVENUE

P51800012139 · promoter Enterprise

Certificate SignedDue 30 Mar 2022

Delivery & Registration

MahaRERA registrationP51800012139
Registered on01 Sep 2017
Promoter-declared completion30 Mar 2022
Current statusCertificate Signed
Against todayabout 52 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8.

BuildingWingsFloorsDeclared completion
KAPADIA AVENUE1G+830 Sep 2021

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 2 times. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
30 Mar 202230 Sep 2021DUE TO THE PANDEMIC AND THE LOCKDOWN THAT WAS IMPOSED THE SUPPLY CHAIN FOR THE CONSTRUCTIONS MATERIAL WAS AFFECTED AND ALSO THERE WAS SHORTAGE OF WORKFORCE DUE TO WHICH THE PROJECT
30 Mar 202230 Mar 2020As the approvals for the project were delayed due to the New TDR Policy (Related to Road Width) And new DCR 2034.

Location, Land & Connectivity

Located at Borivali, Mumbai Suburban, 400064. Per the filed land record, the plot is bounded to the north by CTS NO 698 AND 696, to the south by NALLA, to the east by CTS NO 692 and to the west by CTS 700. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~7 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Andheri MIDC / SEEPZ7 km
Powai / Hiranandani business park10 km
Chhatrapati Shivaji Int'l Airport11 km
Bandra Kurla Complex (BKC)14 km
Lower Parel / Worli business district21 km
Nariman Point / Fort29 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Malad West

Ajmera Arham
possession by Jul 2026 · Vishal Construction
Imperial Hava Hira
possession by Jul 2026 · Shree SAI Realty
Liberte64
possession by Aug 2026 · Jadhwani Infrastructure LLP
Ramdev Veeral Heights
possession by Aug 2026 · Ramdev Associates
Rajgopal Building
possession by Sep 2026 · Harmony AND Prosperity Developer
Shree Hari Krupa
possession by Sep 2026 · Mamtora Foundation

Major developers building in Malad West

Other RERA-registered projects in Mumbai Suburban

Kapil Kunj
declared completion Dec 2018 · Niraj Mansukhlal VED
Karmayog
possession by Mar 2027 · Westin Developers Pvt. LTD
Karmyog
declared completion Dec 2022 · Krishnir Realtors AND Developers
Karuna Sagar CHS LTD
declared completion May 2025 · Khedekar's
Karwari CO-OP HSG Society Redevelopment Crystal Tower
declared completion Dec 2021 · MK Construction
Kashi Bhuvan
declared completion Sep 2025 · Bharat V Kenny

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026