KESHAV ONE

NALASOPARA WEST · KESHAV ENTERPRISES

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Sep 2023declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Sep 2023

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P99000020835

Delivery and registration

When is the project declared for completion?

KESHAV ONE is registered with MahaRERA as P99000020835 and the promoter has declared completion for 30 Sep 2023.

30 Sep 2023

declared completion

36months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP99000020835
Registered on15 May 2019
Promoter-declared completion30 Sep 2023
Current statusCertificate Signed
Against todayabout 36 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for KESHAV ONE record 18 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 18 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Keshav Enterprises is the promoter of record on 51 projects registered with MahaRERA, 9 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

51projects

registered with MahaRERA

9flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for KESHAV ONE in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+5.

BuildingWingsFloorsDeclared completion
KESHAV ONE B TYPE1G+531 Mar 2022

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered30 Sep 2023DELAY OF THE PROJECT IS DUE TO COVID PERIOD AND DELAY IN GETTING OF AMENDED CC.

Location, Land & Connectivity

Located at NALASOPARA WEST, KESHAV ONE,CHANNAKAY PARK,SAMEL PADA,DATTA MANDIR ROAD, Vasai, Palghar, 401203. Per the filed land record, the plot is bounded to the north by OPEN, to the south by OPEN, to the east by 6M W and to the west by EXISTING RD TO THE WEST. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Nallasopara West

Kaneri Heights
possession by Sep 2026 · Shekhar Bhoir AND Others
Kunal Height
possession by Dec 2026 · Shree SAI Builders & Developers
Vimal Classic
possession by Dec 2026 · OM Vimal Developers
Anant Tower E AND F
possession by Dec 2026 · Shantinath Enterprises
Dhananjay Avenue
possession by Dec 2026 · SAI Kiran Builder AND Developers
Sai Baba Nagar Residential With Shopline Building With A B C Wings
Not filing quarterly progress reports · possession by Dec 2026 · Shreeji Associates

Other RERA-registered projects in Palghar

Keshav Srushti
declared completion Dec 2025 · Srushti Realtors
Keziah Enclave
declared completion Dec 2024 · Keziah Construction
KGN Complex
possession by Sep 2026 · KGN Developers
Khatushyam Empire 1
possession by Dec 2028 · Sunrock Constructions LLP
Khushi Aangan Phase II
declared completion Dec 2022 · Khushi Developers
Kiara
possession by Jun 2029 · Niwas Lifespaces LLP

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026