MahaRERA Property Intelligence · Mumbai City

LB ONE

P51900009787 · Worli · promoter Lokhandwala Infrastructure Private

Certificate SignedDue 30 Dec 2025

Delivery & Registration

MahaRERA registrationP51900009787
Registered on22 Aug 2017
Promoter-declared completion30 Dec 2025
Current statusCertificate Signed
Against todayabout 7 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Lokhandwala Infrastructure Private is the promoter of record on 4 projects, of which 1 carries a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+52.

BuildingWingsFloorsDeclared completion
LB ONE1G+52-

Complaints & Orders

6 complaints are on the MahaRERA record for this project, with orders passed in 6. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC00600000019394619/09/2020Nitin Saraf vs Lokhandwala Infrastructure Pvt. Ltd.order passed
CC00600000019509301/12/2020Rajat Gupta vs Lokhandwala Infrastructure Pvt. Ltd.order passed
CC00600000019509601/12/2020Samiksha Arya vs Lokhandwala Infrastructure Pvt. Ltd.order passed
CC00600000019509701/12/2020Akanksha Mehta vs Lokhandwala Infrastructure Pvt. Ltd.order passed
CC00600000019518208/12/2020SVM Properties Private Limited vs Lokhandwala Infrastructure Private Limtiedorder passed
CC00600000019698521/05/2021Ramakant Umashankar Khetan vs Lokhandwala Infrastructure Private Limtiedorder passed

Legal & Litigation

The promoter has declared 9 court cases on this project to MahaRERA. 6 are still pending. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your flat. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Small Causes CourtRAE15922013Closed
Small Causes CourtRAD16292014Closed
Small Causes CourtRAE18432014Pending
Small Causes CourtRAE722015Pending
Bombay City Civil Court24402014Pending
Bombay City Civil Court28242014Pending
Bombay City Civil Court3142015Pending
High Court Of BombayAO50452016Closed
High Court Of Bombay31582016Pending

Location, Land & Connectivity

Located at Worli, Worli Naka, Ward GSouth, Mumbai City, 400018. Per the filed land record, the plot is bounded to the north by GANAPATRAO KADAM MARG, to the south by INDIABULL BLUE, to the east by VICTORIA and to the west by WORLI NAKA. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~1 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Lower Parel / Worli business district1 km
Nariman Point / Fort8 km
Bandra Kurla Complex (BKC)9 km
Chhatrapati Shivaji Int'l Airport11 km
Andheri MIDC / SEEPZ16 km
Powai / Hiranandani business park16 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Worli

DB Turf View
Deregistered by MahaRERA · possession by Dec 2026 · Turf Estate JV
THE Xclusiv
Not filing quarterly progress reports · possession by Dec 2026 · Om Omega Shelters
THE Legacy
possession by Mar 2027 · Sachiv Surinder Sahni
Naman Xana
possession by Aug 2027 · Shree Naman Residency Pvt. Ltd.
47 Race Course
Deregistered by MahaRERA · possession by Dec 2027 · Akshay Sthapatya Pvt. Ltd.
Nishuvi Rehab Phase
Deregistered by MahaRERA · possession by Dec 2027 · Nishuvi Corporation

Major developers building in Worli

Other RERA-registered projects in Mumbai City

LE Palazzo
possession by Aug 2026 · Sri Harsh Developers
Leela Laher
declared completion Dec 2023 · Bineeta
Leela Tara
declared completion Mar 2019 · Sakaar Developers
Lifescapes Altimo
declared completion Mar 2024 · Peccadily Estate Pvt Ltd
Lifescapes Ambar
declared completion Dec 2018 · Rohan Developers Pvt. Ltd.
Lifescapes Aquino
declared completion Jul 2024 · Goodwill Properties Pvt Ltd

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026